    "meta": {
        "built": "2026-08-30T17:58:26+00:00",
        "retrieved": "2026-08-30",
        "record": "City of San Antonio - Bond Project master list",
        "cadence": "The City states this list is updated monthly."
    },
    "money": {
        "approved": 2050000000,
        "spent": 1069468345,
        "spent_pct": 52.2,
        "field_used": "Bond Budget and Bond Expenditures",
        "field_coverage": {
            "bond_budget": 99.2,
            "bond_expenditures": 98.6,
            "total_budget": 25.9
        },
        "do_not_use_total_budget": "The field named \"Total Budget\" is a recorded ZERO on 274 of 370 projects, not a blank, and the record does not say whether that means no separate budget or none entered. Summing it against Total Expenditures reports spending at 602.5% of budget.",
        "a_rate_lives_inside_one_pair": "Four divisions are refused: Total Expenditures by Total Budget, Bond Expenditures by Total Budget, Total Expenditures by Bond Budget, and any of those summed citywide before dividing.",
        "do_not_blend_programmes": "The citywide spend rate is published only beside the two program rates. They are at different stages, and a single blended figure describes neither.",
        "programme_rates": [
            {
                "programme": "2017",
                "spent_pct": 86
            },
            {
                "programme": "2022",
                "spent_pct": 28.5
            }
        ]
    },
    "count": 370,
    "note": "construction_end is a season, never a date. district_kind is single, multi, citywide or none; a project spanning several districts is never split between them. latitude\/longitude is the single point the City recorded, not the extent of the work.",
    "enrichment": {
        "source_packages": [
            "bond-project-line",
            "bond-project-lines",
            "bond-project-points"
        ],
        "projects_with_a_published_scope": 134,
        "projects_with_a_named_vendor": 57,
        "alignments": 134,
        "join_key": "SAPNo",
        "note": "The master list this page is built on does not publish a project number, a scope, a design schedule or a vendor. Sibling packages in the same catalog do, for a subset of the same projects, and they are joined here on the City project number rather than on the project name, which is spelled differently between the files.",
        "corrects_a_published_claim": "This page previously stated that the City publishes no contract or vendor data anywhere in its open data catalog. That was wrong, and it was wrong because the search that produced it swept dataset titles and keywords while vendor names are a column inside a dataset. The City names consultants and contractors on bond projects. Coverage is uneven and runs backwards in time: near complete on the 2012 program, partial on 2017, and absent from the current master list."
    },
    "projects": [
        {
            "project": "Texana Resource Center",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2022",
            "construction_end": "Spring 2024",
            "bond_budget": 0,
            "bond_expenditures": 0,
            "total_budget_sparse_field": 0,
            "total_expenditures": 0,
            "latitude": 29.43231,
            "longitude": -98.49268,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "1604\/Bulverde Road Turanarounds",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Spring 2019",
            "bond_budget": 500000,
            "bond_expenditures": 477597,
            "total_budget_sparse_field": 477597,
            "total_expenditures": 477597,
            "latitude": 29.60076,
            "longitude": -98.41812,
            "city_project_no": "23-01558",
            "scope": "Leverage funds toward construction of turnarounds under the North 1604\/Bulverde intersection. Cost reflects City of San Antonio\u2019s contribution to a proposed federally funded project.",
            "design_start": "Fall 2017",
            "design_end": "Spring 2018",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Applewhite Road Intersection (South of Watson Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03,04",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 1000000,
            "bond_expenditures": 1000000,
            "total_budget_sparse_field": 1200000,
            "total_expenditures": 1200000,
            "latitude": 29.25382,
            "longitude": -98.54931,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Bitters Road Intersection & Sidewalks (Savannah Pass to Blanco Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2022",
            "bond_budget": 5080000,
            "bond_expenditures": 4087171,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5226835,
            "latitude": 29.5805,
            "longitude": -98.50784,
            "city_project_no": "23-01560",
            "scope": "Construct intersection, traffic signal and sidewalk improvements.  Includes adding left-turn lanes at Savannah Pass and Partridge Trail; and a dedicated right-turn lane from Bitters onto northbound Blanco Road.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Garcia & Wright Consulting Engr.",
            "contractor": null
        },
        {
            "project": "Broadway Street Corridor (East Houston Street to East Hildebrand Avenue)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01,02",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2020",
            "construction_end": "Fall 2024",
            "bond_budget": 42000000,
            "bond_expenditures": 27918535,
            "total_budget_sparse_field": 0,
            "total_expenditures": 63445294,
            "latitude": 29.43245,
            "longitude": -98.48284,
            "city_project_no": "23-01561",
            "scope": "Reconstruct Broadway from E. Houston to Hildebrand with curbs, sidewalks, driveway approaches, bicycle amenities, lighting, drainage and traffic improvements as appropriate and within available funds. City funding will leverage state and federal funding.",
            "design_start": "Summer 2018",
            "design_end": "Fall 2020",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brooks City Base Inner Circle Road (Louis Bauer Drive to Research Plaza)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Summer 2022",
            "bond_budget": 3000000,
            "bond_expenditures": 2877398,
            "total_budget_sparse_field": 2921348,
            "total_expenditures": 2921348,
            "latitude": 29.33952,
            "longitude": -98.44526,
            "city_project_no": "23-01562",
            "scope": "Extend and improve Inner Circle from Louis Bauer to Research Plaza.",
            "design_start": "Spring 2017",
            "design_end": "Winter 2020",
            "consultant": "Pape-Dawson Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "Brooks City Base South New Braunfels Avenue (Lyster Road to Aviation Landing)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2021",
            "bond_budget": 10400000,
            "bond_expenditures": 10239257,
            "total_budget_sparse_field": 10591257,
            "total_expenditures": 10591257,
            "latitude": 29.33789,
            "longitude": -98.43242,
            "city_project_no": "23-01563",
            "scope": "Extend New Braunfels within Brooks City Base to proposed intersection with Lyster Road, continuing to the intersection of Aviation Landing.",
            "design_start": "Spring 2017",
            "design_end": "Summer 2018",
            "consultant": "Pape-Dawson Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "District 6 Intersection Improvements",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Fall 2026",
            "bond_budget": 5000000,
            "bond_expenditures": 1063676,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3983115,
            "latitude": 29.44886,
            "longitude": -98.69022,
            "city_project_no": "23-03886",
            "scope": "Construct pedestrian mobility improvement projects as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Summer 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brooks City Base Stinson Corridor (Research Plaza to South Presa Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Spring 2022",
            "bond_budget": 10000000,
            "bond_expenditures": 8897339,
            "total_budget_sparse_field": 9149139,
            "total_expenditures": 9149139,
            "latitude": 29.33565,
            "longitude": -98.44676,
            "city_project_no": "23-01564",
            "scope": "New roadway alignment of Research Plaza to South Presa.",
            "design_start": "Summer 2017",
            "design_end": "Summer 2020",
            "consultant": "Pape-Dawson Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "Bulverde Road Phase 1 (Butterleigh Drive to North of Quiet Meadow Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Fall 2024",
            "bond_budget": 17000000,
            "bond_expenditures": 10557807,
            "total_budget_sparse_field": 0,
            "total_expenditures": 12549199,
            "latitude": 29.57773,
            "longitude": -98.41967,
            "city_project_no": "23-01565",
            "scope": "Reconstruct and widen Bulverde roadway with curbs, sidewalks, driveway approaches, traffic signal and drainage improvements, as appropriate and within available funding. This is a continuation of Bexar County's Street and Drainage Improvements Project to realign Jung Road to Quiet Meadow.",
            "design_start": "Winter 2018",
            "design_end": "Fall 2019",
            "consultant": "LNV, Inc.",
            "contractor": null
        },
        {
            "project": "Bynum Avenue  (West Gerald Avenue to Southwest Military Drive)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2022",
            "bond_budget": 7730000,
            "bond_expenditures": 7151639,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8566562,
            "latitude": 29.36301,
            "longitude": -98.56133,
            "city_project_no": "23-01566",
            "scope": "Reconstruct Bynum from W. Gerald to S.W. Military with curbs, sidewalks, driveway approaches, drainage and other improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "IDCUS, Inc.",
            "contractor": null
        },
        {
            "project": "Camaron Street (West Houston Street to Fox Tech High School)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Winter 2023",
            "bond_budget": 4500000,
            "bond_expenditures": 4166534,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4940775,
            "latitude": 29.42938,
            "longitude": -98.4962,
            "city_project_no": "23-01567",
            "scope": "Develop pedestrian corridor improvements, as appropriate on Camaron and Kingsbury from W. Houston to Flores near Fox Tech High School.",
            "design_start": "Winter 2018",
            "design_end": "Spring 2020",
            "consultant": "Michael Baker International, Inc.",
            "contractor": null
        },
        {
            "project": "Commerce Street (St. Mary\u2019s Street to Santa Rosa Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Fall 2023",
            "bond_budget": 6000000,
            "bond_expenditures": 6840588,
            "total_budget_sparse_field": 0,
            "total_expenditures": 11692538,
            "latitude": 29.42517,
            "longitude": -98.4948,
            "city_project_no": "23-01568",
            "scope": "Reconstruct Commerce Street from St. Mary\u2019s to Santa Rosa.  Includes wayfinding signage, pedestrian amenities, and streetscape improvements as appropriate and within available funding.  These funds will supplement the 2012 Bond Program project.",
            "design_start": null,
            "design_end": null,
            "consultant": "Chiang Patel & Yerby, Inc.",
            "contractor": null
        },
        {
            "project": "Commerce Street (Frio Street to Santa Rosa Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2026",
            "bond_budget": 14000000,
            "bond_expenditures": 5167742,
            "total_budget_sparse_field": 0,
            "total_expenditures": 13448506,
            "latitude": 29.42576,
            "longitude": -98.50093,
            "city_project_no": "23-01569",
            "scope": "Reconstruct Commerce from Santa Rosa to Frio.  Includes pedestrian amenities, and streetscape improvements as appropriate and within available funding.  This is a continuation of the 2012 Bond Program project.",
            "design_start": "Spring 2018",
            "design_end": "Winter 2021",
            "consultant": "Chiang Patel & Yerby, Inc.",
            "contractor": null
        },
        {
            "project": "DeZavala Road (I-10 Frontage Road to Lockhill Selma Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Winter 2021",
            "bond_budget": 15500000,
            "bond_expenditures": 14869701,
            "total_budget_sparse_field": 17190911,
            "total_expenditures": 17190911,
            "latitude": 29.56902,
            "longitude": -98.57679,
            "city_project_no": "23-01570",
            "scope": "Reconstruct and widen DeZavala from I-10 to Lockhill Selma.  Includes curbs, sidewalks, driveway approaches, improved railroad crossing, intersection signal modifications and drainage improvements as appropriate and within available funding.",
            "design_start": null,
            "design_end": null,
            "consultant": "Camacho-Hernandez & Associates",
            "contractor": "Curran Contracting Company"
        },
        {
            "project": "District 1 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Summer 2026",
            "bond_budget": 9000000,
            "bond_expenditures": 7283574,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10427523,
            "latitude": 29.47416,
            "longitude": -98.50786,
            "city_project_no": "23-01571",
            "scope": "Construct pedestrian mobility and street improvement projects.",
            "design_start": "Winter 2018",
            "design_end": "Spring 2023",
            "consultant": "MW Cude Engineers, LLC",
            "contractor": null
        },
        {
            "project": "District 2 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Winter 2023",
            "bond_budget": 4800000,
            "bond_expenditures": 4387224,
            "total_budget_sparse_field": 4494824,
            "total_expenditures": 4494824,
            "latitude": 29.42508,
            "longitude": -98.45226,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 3 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2018",
            "construction_end": "Winter 2024",
            "bond_budget": 9000000,
            "bond_expenditures": 8690786,
            "total_budget_sparse_field": 0,
            "total_expenditures": 9169395,
            "latitude": 29.36128,
            "longitude": -98.4929,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Winter 2024",
            "bond_budget": 7000000,
            "bond_expenditures": 6695206,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6883685,
            "latitude": 29.35523,
            "longitude": -98.60867,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 5 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Fall 2023",
            "bond_budget": 7438000,
            "bond_expenditures": 6113840,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7042272,
            "latitude": 29.40768,
            "longitude": -98.53878,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 6 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2019",
            "construction_end": "Summer 2026",
            "bond_budget": 5000000,
            "bond_expenditures": 3202488,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4296581,
            "latitude": 29.41559,
            "longitude": -98.62403,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 Sidewalks",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Fall 2023",
            "bond_budget": 2800000,
            "bond_expenditures": 2279339,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2318252,
            "latitude": 29.47096,
            "longitude": -98.53253,
            "city_project_no": "23-01577",
            "scope": "Construct sidewalk improvements along Wilson Boulevard (Club Drive to Babcock Road), west side of Fredericksburg Road (N. Zarzamora to Balcones Heights Boulevard), one side of Loma Linda Drive (Babcock Road to Williamsburg Place), west side of Lake Boulevard (Club Drive to West Woodlawn Avenue), Benrus Boulevard and other District 7 sidewalk projects as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Fall 2022",
            "consultant": "Jacobs Engineering Group, Inc.",
            "contractor": null
        },
        {
            "project": "District 9 Pedestrian Mobility & Streets",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2018",
            "construction_end": "Fall 2022",
            "bond_budget": 4000000,
            "bond_expenditures": 3085096,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3252652,
            "latitude": 29.54695,
            "longitude": -98.45825,
            "city_project_no": "23-01578",
            "scope": "Construct pedestrian mobility and street improvement projects.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2022",
            "consultant": "Slay Engineering Company, Inc.",
            "contractor": null
        },
        {
            "project": "Enrique M. Barrera Parkway Phase 1 (Old Highway 90 Area)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Winter 2024",
            "bond_budget": 9000000,
            "bond_expenditures": 9264657,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10618069,
            "latitude": 29.42408,
            "longitude": -98.57888,
            "city_project_no": "23-01579",
            "scope": "Improve Enrique M. Barrera Parkway corridor with street, drainage and sidewalk improvements as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Spring 2020",
            "consultant": "AIA Engineers, Ltd.",
            "contractor": null
        },
        {
            "project": "Evans Road (Highway 281 to Caliza Drive)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 2700000,
            "bond_expenditures": 2228853,
            "total_budget_sparse_field": 2270983,
            "total_expenditures": 2270983,
            "latitude": 29.63999,
            "longitude": -98.44165,
            "city_project_no": "23-01580",
            "scope": "Intersection and corridor improvements on Evans from Hwy 281 to Caliza Drive.  Includes medians, acceleration\/deceleration lanes and traffic signal improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "WSP USA, Inc.",
            "contractor": null
        },
        {
            "project": "Fort Sam ISD New Roadway (Winans Road to Rittiman Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Summer 2021",
            "bond_budget": 1725000,
            "bond_expenditures": 1523094,
            "total_budget_sparse_field": 1723094,
            "total_expenditures": 1723094,
            "latitude": 29.4815,
            "longitude": -98.41866,
            "city_project_no": "23-01581",
            "scope": "Construct a new two-lane roadway from Winans to Rittiman adjacent to John James Park.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Garcia & Wright Consulting Engr.",
            "contractor": null
        },
        {
            "project": "Fredericksburg Road (North Flores Street to West Woodlawn Avenue)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2021",
            "construction_end": "Winter 2023",
            "bond_budget": 8000000,
            "bond_expenditures": 7080987,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8087447,
            "latitude": 29.44737,
            "longitude": -98.50935,
            "city_project_no": "23-01582",
            "scope": "Construct corridor improvements on Fredericksburg from Flores to Woodlawn.  Includes drainage, pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Fall 2020",
            "consultant": "Poznecki-Camarillo, Inc.",
            "contractor": null
        },
        {
            "project": "Goliad Road (Fair Avenue to East Southcross Boulevard)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Spring 2023",
            "bond_budget": 12937000,
            "bond_expenditures": 10271037,
            "total_budget_sparse_field": 0,
            "total_expenditures": 12581353,
            "latitude": 29.38029,
            "longitude": -98.45303,
            "city_project_no": "23-01583",
            "scope": "Reconstruct Goliad from Fair to Southcross with curbs, sidewalks, driveway approaches, drainage and other improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "Camacho-Hernandez & Associates",
            "contractor": null
        },
        {
            "project": "Hardberger Park (Streets)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08,09",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Fall 2018",
            "construction_end": "Fall 2020",
            "bond_budget": 7500000,
            "bond_expenditures": 7500000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 15499999,
            "latitude": 29.55839,
            "longitude": -98.52582,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 6 Parks",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 828000,
            "bond_expenditures": 814230,
            "total_budget_sparse_field": 814230,
            "total_expenditures": 814230,
            "latitude": 29.41085,
            "longitude": -98.60783,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hardy Oak Boulevard and Huebner Road Extensions",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2017",
            "construction_end": "Spring 2019",
            "bond_budget": 6300000,
            "bond_expenditures": 5883585,
            "total_budget_sparse_field": 5883585,
            "total_expenditures": 5883585,
            "latitude": 29.62505,
            "longitude": -98.48183,
            "city_project_no": "23-01585",
            "scope": "Leverage funding to construct new roads through the Classen-Steubing Ranch property.",
            "design_start": null,
            "design_end": null,
            "consultant": "Developer (Pape Dawson Engineers)",
            "contractor": null
        },
        {
            "project": "Harry Wurzbach Road\/Austin Highway Connectors",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Winter 2023",
            "bond_budget": 3000000,
            "bond_expenditures": 2421067,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2554503,
            "latitude": 29.494,
            "longitude": -98.43317,
            "city_project_no": "23-01586",
            "scope": "Leverage funding to construct two traffic ramps at Harry Wurzbach\/Austin Highway. Project design and initial construction was funded through the City of San Antonio and Texas Department of Transportation.",
            "design_start": null,
            "design_end": null,
            "consultant": "Civil Engineering Consultants",
            "contractor": null
        },
        {
            "project": "Heath Road\/Grissom Road Intersection",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Summer 2022",
            "bond_budget": 1100000,
            "bond_expenditures": 941055,
            "total_budget_sparse_field": 1192920,
            "total_expenditures": 1192920,
            "latitude": 29.48154,
            "longitude": -98.6348,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hemisfair Park Streets Phase 2",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2022",
            "construction_end": "Spring 2023",
            "bond_budget": 5000000,
            "bond_expenditures": 3709797,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4399673,
            "latitude": 29.41938,
            "longitude": -98.4843,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Ingram Road (Potranco Road to Dead End)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 1000000,
            "bond_expenditures": 820837,
            "total_budget_sparse_field": 825008,
            "total_expenditures": 825008,
            "latitude": 29.44858,
            "longitude": -98.65427,
            "city_project_no": "23-01589",
            "scope": "Construct road extension from Potranco to Ingram dead end.  Includes curbs, sidewalks, bike facilities and drainage improvements as appropriate and within available funding.",
            "design_start": "Winter 2018",
            "design_end": "Winter 2019",
            "consultant": "Developer (KFW Engineers)",
            "contractor": null
        },
        {
            "project": "Jones Maltsberger Road\/Burning Trail Intersection",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Summer 2020",
            "bond_budget": 1600000,
            "bond_expenditures": 1276918,
            "total_budget_sparse_field": 1290428,
            "total_expenditures": 1290428,
            "latitude": 29.57014,
            "longitude": -98.4501,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lamar Street (Austin Street to North New Braunfels Avenue)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2017",
            "construction_end": "Spring 2020",
            "bond_budget": 2500000,
            "bond_expenditures": 2052024,
            "total_budget_sparse_field": 3962797,
            "total_expenditures": 3962797,
            "latitude": 29.43143,
            "longitude": -98.47025,
            "city_project_no": "23-01591",
            "scope": "Reconstruct Lamar Street from Austin Street to N. New Braunfels with curbs, sidewalks and driveway approaches as appropriate and within available funding.",
            "design_start": null,
            "design_end": null,
            "consultant": "Bain Medina Bain, Inc.",
            "contractor": "San Antonio Constructors, LTD"
        },
        {
            "project": "Lone Star Boulevard (Area Streets)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 62000,
            "bond_expenditures": 62657,
            "total_budget_sparse_field": 62657,
            "total_expenditures": 62657,
            "latitude": 29.40265,
            "longitude": -98.49061,
            "city_project_no": "23-01592",
            "scope": "Reconstruct and widen Lone Star Boulevard.  Includes pedestrian and bicycle facilities amenities as well as intersection improvements as appropriate and within available funding.",
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Medical Center (Louis Pasteur Drive at Babcock Road Intersection)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2018",
            "construction_end": "Winter 2019",
            "bond_budget": 1600000,
            "bond_expenditures": 904243,
            "total_budget_sparse_field": 904243,
            "total_expenditures": 904243,
            "latitude": 29.50002,
            "longitude": -98.57814,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Medical Center Phase 10 (Ewing Halsell Drive\/Louis Pasteur Drive Intersection)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2018",
            "construction_end": "Winter 2019",
            "bond_budget": 7170000,
            "bond_expenditures": 3544141,
            "total_budget_sparse_field": 3898146,
            "total_expenditures": 3898146,
            "latitude": 29.50878,
            "longitude": -98.57002,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Mission Road (San Antonio River to Southeast Military Drive)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Fall 2022",
            "bond_budget": 2000000,
            "bond_expenditures": 1271581,
            "total_budget_sparse_field": 2591370,
            "total_expenditures": 2591370,
            "latitude": 29.3399,
            "longitude": -98.46835,
            "city_project_no": "23-01595",
            "scope": "Construct streetscape improvements along Mission Road.  Includes lighting, trail enhancements and other improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Winter 2019",
            "consultant": "Garza EMC, LLC",
            "contractor": null
        },
        {
            "project": "Monticello Park (Area Streets)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 3936000,
            "bond_expenditures": 3423602,
            "total_budget_sparse_field": 3540610,
            "total_expenditures": 3540610,
            "latitude": 29.4641,
            "longitude": -98.53054,
            "city_project_no": "23-01596",
            "scope": "Reconstruct area streets to include curbs, sidewalks, driveway approaches and other improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Fernandez, Frazer, White & Assoc",
            "contractor": null
        },
        {
            "project": "North Flores Street\/Fredericksburg Road (Five Points)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 3000000,
            "bond_expenditures": 2933925,
            "total_budget_sparse_field": 3485250,
            "total_expenditures": 3485250,
            "latitude": 29.44163,
            "longitude": -98.50332,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "North Main Avenue & Soledad Street (Pecan Street to Navarro Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2024",
            "bond_budget": 9000000,
            "bond_expenditures": 8660840,
            "total_budget_sparse_field": 0,
            "total_expenditures": 13135033,
            "latitude": 29.43084,
            "longitude": -98.49339,
            "city_project_no": "23-01598",
            "scope": "Reconstruct Main and Soledad between Pecan and Navarro.  Includes pedestrian amenities and streetscape improvements as appropriate and within available funding. This is a continuation of the 2012 Bond Program project.",
            "design_start": "Summer 2018",
            "design_end": "Summer 2020",
            "consultant": "Lockwood, Andrews & Newnam, Inc.",
            "contractor": null
        },
        {
            "project": "North New Braunfels Avenue Phase 1 (East Houston Street to Burleson Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2021",
            "construction_end": "Fall 2023",
            "bond_budget": 9000000,
            "bond_expenditures": 7197277,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10746239,
            "latitude": 29.42889,
            "longitude": -98.46104,
            "city_project_no": "23-01599",
            "scope": "Improve N. New Braunfels corridor from E. Houston to Burleson with construction of new sidewalks and other street amenities as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Fall 2020",
            "consultant": "Freese and Nichols, Inc.",
            "contractor": null
        },
        {
            "project": "North St. Mary\u2019s Street (East Mistletoe Avenue to West Josephine Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Summer 2023",
            "bond_budget": 7000000,
            "bond_expenditures": 7630002,
            "total_budget_sparse_field": 0,
            "total_expenditures": 15084534,
            "latitude": 29.45084,
            "longitude": -98.48658,
            "city_project_no": "23-01600",
            "scope": "Improve N. St. Mary's from Mistletoe to Josephine including sidewalk connectivity, intersection improvements and signal enhancements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2020",
            "consultant": "Gonzalez De La Garza & Associates",
            "contractor": null
        },
        {
            "project": "O.P. Schnabel Park Entrance & Bridge",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Summer 2021",
            "bond_budget": 1100000,
            "bond_expenditures": 916079,
            "total_budget_sparse_field": 1183643,
            "total_expenditures": 1183643,
            "latitude": 29.53292,
            "longitude": -98.64263,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Probandt Street (South Alamo Street to US Highway 90)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 9000000,
            "bond_expenditures": 1238402,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1708140,
            "latitude": 29.40339,
            "longitude": -98.49502,
            "city_project_no": "23-01602",
            "scope": "Corridor improvements on Probandt from S. Alamo to Hwy 90.  Includes pedestrian amenities, drainage, traffic and other improvements as appropriate and within available funding.  City funding will leverage State funding.",
            "design_start": "Summer 2018",
            "design_end": "Winter 2027",
            "consultant": "Kimley-Horn and Associates, Inc.",
            "contractor": null
        },
        {
            "project": "Prue Road (Babcock Road to Laureate Drive)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Fall 2025",
            "bond_budget": 27600000,
            "bond_expenditures": 19661669,
            "total_budget_sparse_field": 0,
            "total_expenditures": 39164454,
            "latitude": 29.54473,
            "longitude": -98.60082,
            "city_project_no": "23-01603",
            "scope": "Reconstruct and widen Prue from Babcock to Laureate.  Includes curbs, sidewalks, driveway approaches, signal modifications and drainage improvements as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Summer 2020",
            "consultant": "Michael Baker International, Inc.",
            "contractor": "JJ Abrams LP"
        },
        {
            "project": "Al Rohde Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Winter 2025",
            "bond_budget": 500000,
            "bond_expenditures": 499472,
            "total_budget_sparse_field": 0,
            "total_expenditures": 685870,
            "latitude": 29.5568,
            "longitude": -98.62525,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rittiman Road (I-35 to Castle Cross Drive)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 4000000,
            "bond_expenditures": 3722782,
            "total_budget_sparse_field": 6629155,
            "total_expenditures": 6629155,
            "latitude": 29.48408,
            "longitude": -98.38728,
            "city_project_no": "23-01604",
            "scope": "Improve intersection of I-35 and Rittiman to include construction of a right-turn lane and pavement improvements from I-35 to Castle Cross as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "GGC Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "Roosevelt Avenue (I-10 to South St. Mary\u2019s Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2022",
            "construction_end": "Spring 2023",
            "bond_budget": 5000000,
            "bond_expenditures": 4590246,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6235703,
            "latitude": 29.39922,
            "longitude": -98.48632,
            "city_project_no": "23-01605",
            "scope": "Corridor improvements on Roosevelt  and S. St. Mary\u2019s to include bicycle facilities, sidewalks, landscaping and ADA access under the Union Pacific Railroad bridge.",
            "design_start": "Summer 2018",
            "design_end": "Spring 2021",
            "consultant": "Civil Engineering Consultants",
            "contractor": null
        },
        {
            "project": "Roosevelt Avenue (US Highway 90 to Southeast Loop 410)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2027",
            "construction_end": "Spring 2029",
            "bond_budget": 8000000,
            "bond_expenditures": 1853707,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4803389,
            "latitude": 29.38005,
            "longitude": -98.48213,
            "city_project_no": "23-01606",
            "scope": "Improvements from Hwy 90 to Mission San Jose (north of SE Military).  Includes pedestrian amenities and enhancements as appropriate and within available funding.  City funding will leverage State funding.",
            "design_start": "Fall 2018",
            "design_end": "Spring 2026",
            "consultant": "Civil Engineering Consultants",
            "contractor": null
        },
        {
            "project": "San Saba Street (Nueva Street to Martin Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2026",
            "bond_budget": 6000000,
            "bond_expenditures": 5896515,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8816590,
            "latitude": 29.42655,
            "longitude": -98.50005,
            "city_project_no": "23-01607",
            "scope": "Roadway improvements on San Saba from Nueva to Martin.  Includes  pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Fall 2018",
            "design_end": "Winter 2021",
            "consultant": "Moore Iacofano Goltsman, Inc.",
            "contractor": null
        },
        {
            "project": "Santa Rosa Street  (C\u00e9sar E. Ch\u00e1vez Boulevard to Martin Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2026",
            "bond_budget": 12000000,
            "bond_expenditures": 11723388,
            "total_budget_sparse_field": 0,
            "total_expenditures": 19430325,
            "latitude": 29.42529,
            "longitude": -98.49809,
            "city_project_no": "23-01608",
            "scope": "Reconstruct Santa Rosa from C\u00e9sar E. Ch\u00e1vez to Martin.  Includes pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Winter 2021",
            "consultant": "Pape-Dawson Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "South Alamo Street Improvements (Market Street to East C\u00e9sar E. Ch\u00e1vez Boulevard)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2022",
            "construction_end": "Spring 2026",
            "bond_budget": 9000000,
            "bond_expenditures": 6424243,
            "total_budget_sparse_field": 0,
            "total_expenditures": 47120114,
            "latitude": 29.42074,
            "longitude": -98.48805,
            "city_project_no": "23-01609",
            "scope": "Reconstruct Alamo St. from  Market to C\u00e9sar E. Ch\u00e1vez.  Includes pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Winter 2018",
            "design_end": "Fall 2020",
            "consultant": "Moore Iacofano Goltsman, Inc.",
            "contractor": null
        },
        {
            "project": "South Presa Street (Southeast Military Drive to Southcross Boulevard)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2022",
            "construction_end": "Spring 2024",
            "bond_budget": 5000000,
            "bond_expenditures": 4585867,
            "total_budget_sparse_field": 0,
            "total_expenditures": 19456575,
            "latitude": 29.36364,
            "longitude": -98.46795,
            "city_project_no": "23-01610",
            "scope": "Construct corridor improvements from Military to Southcross.  Includes pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "RPS Klotz Associates",
            "contractor": null
        },
        {
            "project": "South Zarzamora Street\/Applewhite Road Intersection",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Fall 2021",
            "bond_budget": 900000,
            "bond_expenditures": 756265,
            "total_budget_sparse_field": 2531561,
            "total_expenditures": 2531561,
            "latitude": 29.29751,
            "longitude": -98.54731,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "South Zarzamora Street Overpass at Union Pacific Railroad\/Frio City Road",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 10000000,
            "bond_expenditures": 4292538,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10601622,
            "latitude": 29.3967,
            "longitude": -98.53113,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Southcross Boulevard (I-37 to I-35)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Spring 2022",
            "bond_budget": 5000000,
            "bond_expenditures": 4769915,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5019067,
            "latitude": 29.36877,
            "longitude": -98.4888,
            "city_project_no": "23-01613",
            "scope": "Construct corridor improvements along Southcross from I-37 to I-35. Includes pedestrian amenities and enhancements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Brown & Gay Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "The Alamo (Area Streets)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Summer 2026",
            "bond_budget": 13736000,
            "bond_expenditures": 12566106,
            "total_budget_sparse_field": 0,
            "total_expenditures": 13711982,
            "latitude": 29.42572,
            "longitude": -98.48693,
            "city_project_no": "23-01614",
            "scope": "Leverage funding for the design and construction of improvements in the area around The Alamo as appropriate and as identified in The Alamo Master Plan and within available funding.",
            "design_start": "Spring 2019",
            "design_end": "Spring 2023",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Thomas Jefferson High School (Area Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 3600000,
            "bond_expenditures": 3042124,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3186042,
            "latitude": 29.46642,
            "longitude": -98.53693,
            "city_project_no": "23-01615",
            "scope": "Construct street improvements including Wilson Boulevard median in the Jefferson High School area.  Improvements include underground utility conversion at the intersection of Wilson Boulevard and Donaldson Avenue, Wilson Boulevard and Club Drive.  Includes sidewalks, lighting, landscaping, thespian island fountain restoration and other improvements as appropriate and within available funding.",
            "design_start": "Summer 2018",
            "design_end": "Winter 2020",
            "consultant": "Moy Tarin Ramirez Engineers, LLC",
            "contractor": null
        },
        {
            "project": "Thousand Oaks Drive (Wetmore Road to Perrin Beitel Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 3000000,
            "bond_expenditures": 2857170,
            "total_budget_sparse_field": 4878153,
            "total_expenditures": 4878153,
            "latitude": 29.55594,
            "longitude": -98.41462,
            "city_project_no": "23-01616",
            "scope": "Reconstruct outside lanes along Thousand Oaks from Wetmore to Perrin Beitel. Includes  complete pavement improvements as appropriate and within available funding.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Jones & Carter, Inc.",
            "contractor": null
        },
        {
            "project": "West Commerce Street (Frio Street to Colorado Street)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Summer 2023",
            "bond_budget": 10000000,
            "bond_expenditures": 9500659,
            "total_budget_sparse_field": 0,
            "total_expenditures": 14630576,
            "latitude": 29.42643,
            "longitude": -98.50739,
            "city_project_no": "23-01617",
            "scope": "Improvements to Commerce corridor from Frio to Colorado.  Includes reconfiguring lanes on bridge, wider sidewalks, bike facilities and other improvements as appropriate and within available funding.",
            "design_start": "Winter 2017",
            "design_end": "Spring 2020",
            "consultant": "Bain Medina Bain, Inc.",
            "contractor": null
        },
        {
            "project": "West Military Drive & Ingram Road Connectors",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 10000000,
            "bond_expenditures": 8723479,
            "total_budget_sparse_field": 0,
            "total_expenditures": 13881842,
            "latitude": 29.452,
            "longitude": -98.64959,
            "city_project_no": "23-01618",
            "scope": "Construct road extensions of W. Military (dead end to Potranco) and Ingram connector. Includes curbs, sidewalks, bike facilities, traffic signal and drainage improvements as appropriate and within available funding.  City funding will leverage developer funds.",
            "design_start": "Winter 2018",
            "design_end": "Winter 2019",
            "consultant": "Developer (KFW Engineers)",
            "contractor": null
        },
        {
            "project": "World Heritage Trail Signage & Wayfinding",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Winter 2023",
            "bond_budget": 5000000,
            "bond_expenditures": 3232963,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4459400,
            "latitude": 29.37149,
            "longitude": -98.4872,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Wurzbach Road (Northwest Military Highway to Fredericksburg Road)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08,09",
            "district": null,
            "district_kind": "multi",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 2000000,
            "bond_expenditures": 344746,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1829482,
            "latitude": 29.5256,
            "longitude": -98.56777,
            "city_project_no": "23-01620",
            "scope": "Leverage funds for improvements at key intersections along the Wurzbach Corridor. Cost reflects City of San Antonio's contribution to a proposed federal and state funded project.",
            "design_start": "Winter 2020",
            "design_end": "Summer 2024",
            "consultant": "Texas Department of Transportation",
            "contractor": null
        },
        {
            "project": "Public Art (Streets)",
            "programme": "2017",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Summer 2019",
            "construction_end": "Winter 2027",
            "bond_budget": 4449000,
            "bond_expenditures": 2832153,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3914825,
            "latitude": 29.42605,
            "longitude": -98.49912,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Auldine Drive & Burr Oak Drive (Alley to Outfall)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Spring 2023",
            "bond_budget": 2800000,
            "bond_expenditures": 2800000,
            "total_budget_sparse_field": 4744925,
            "total_expenditures": 4744925,
            "latitude": 29.54036,
            "longitude": -98.53138,
            "city_project_no": "23-01622",
            "scope": "Reconstruct alleyway and improvements to existing storm drain system and outfall in the Dreamland Oaks area to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Winter 2020",
            "consultant": "HNTB Corporation",
            "contractor": null
        },
        {
            "project": "Barbara Drive Drainage Phase 2",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Summer 2022",
            "bond_budget": 8700000,
            "bond_expenditures": 8525519,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8878659,
            "latitude": 29.5032,
            "longitude": -98.4927,
            "city_project_no": "23-01623",
            "scope": "Continuation of a multi-phase improvement project to relocate the floodplain away from structures.  This proposed phase will replace a section of existing undersized storm drain system to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "Halff Associates, INC.",
            "contractor": null
        },
        {
            "project": "Beitel Creekway",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Fall 2017",
            "construction_end": "Winter 2019",
            "bond_budget": 2000000,
            "bond_expenditures": 1985356,
            "total_budget_sparse_field": 1985356,
            "total_expenditures": 1985356,
            "latitude": 29.53688,
            "longitude": -98.39014,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Belfast Drive & Janda Susan Road Area Phase 2",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Spring 2019",
            "bond_budget": 2618000,
            "bond_expenditures": 2145142,
            "total_budget_sparse_field": 2768235,
            "total_expenditures": 2768235,
            "latitude": 29.51083,
            "longitude": -98.4698,
            "city_project_no": "23-01625",
            "scope": "Continuation of 2012 Bond Project to provide flooding relief to neighborhood streets and properties. This phase includes continuation of a storm drain system and reconstruction of affected streets which may include curbs, sidewalks and driveway approaches.",
            "design_start": null,
            "design_end": null,
            "consultant": "Stantec",
            "contractor": "E-Z Bel Construction, LLC"
        },
        {
            "project": "Blossom Park (Lotus Blossom Street)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 1400000,
            "bond_expenditures": 1044254,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1247883,
            "latitude": 29.55331,
            "longitude": -98.46331,
            "city_project_no": "23-01626",
            "scope": "Channel improvements to relieve area flooding and channel erosion to include curbs, sidewalks and driveway approaches.",
            "design_start": "Summer 2018",
            "design_end": "Spring 2019",
            "consultant": "CNG Engineering, PLL",
            "contractor": null
        },
        {
            "project": "Cedarhurst Drive Area (Dumont Drive to Eaglerock Drive)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Fall 2021",
            "bond_budget": 9170000,
            "bond_expenditures": 7554412,
            "total_budget_sparse_field": 8395352,
            "total_expenditures": 8395352,
            "latitude": 29.39067,
            "longitude": -98.64477,
            "city_project_no": "23-01627",
            "scope": "Construction of a storm drain system along Cedarhurst Drive and improvements to the existing drainage outfall to provide flooding relief to Springvale neighborhood streets and properties.  This proposed phase includes street reconstruction, curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Maestas & Associates, Inc.",
            "contractor": null
        },
        {
            "project": "Eisenhauer Road\/Northwood-Devonshire Drive Area Phase 1",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Spring 2023",
            "bond_budget": 8000000,
            "bond_expenditures": 6745797,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8040803,
            "latitude": 29.49993,
            "longitude": -98.4383,
            "city_project_no": "23-01628",
            "scope": "Channel improvements to relieve flooding to affected areas during major storm events at street crossings. Project allows for future phases to address street flooding along Devonshire Drive, Seidel Road, Vandiver Road and Eisenhauer Road to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Winter 2018",
            "design_end": "Spring 2020",
            "consultant": "CDS Muery",
            "contractor": null
        },
        {
            "project": "Esma Street Area",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Spring 2021",
            "bond_budget": 9166000,
            "bond_expenditures": 7504467,
            "total_budget_sparse_field": 0,
            "total_expenditures": 9387551,
            "latitude": 29.32795,
            "longitude": -98.42328,
            "city_project_no": "23-01629",
            "scope": "Construction of a storm drain system in the Esma Street area to provide flooding relief to neighborhood streets and properties to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Bain Medina Bain, Inc.",
            "contractor": null
        },
        {
            "project": "North New Braunfels Avenue (Comprehensive Drainage Study)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 300000,
            "bond_expenditures": 300000,
            "total_budget_sparse_field": 300000,
            "total_expenditures": 300000,
            "latitude": 29.48742,
            "longitude": -98.45923,
            "city_project_no": "23-01630",
            "scope": "Leverage funding toward the completion of a comprehensive drainage study to identify how best to address drainage of North New Braunfels area.",
            "design_start": "Fall 2017",
            "design_end": "Fall 2018",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Panther Springs Creek Restoration",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2021",
            "construction_end": "Winter 2022",
            "bond_budget": 1100000,
            "bond_expenditures": 913270,
            "total_budget_sparse_field": 0,
            "total_expenditures": 913270,
            "latitude": 29.62264,
            "longitude": -98.51687,
            "city_project_no": "23-01631",
            "scope": "Improvements to the existing natural channel to improve flow and remove standing water.",
            "design_start": "Winter 2019",
            "design_end": "Winter 2021",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Paso Del Norte Street (Shady Oaks)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2021",
            "construction_end": "Spring 2022",
            "bond_budget": 4318000,
            "bond_expenditures": 2954991,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3272746,
            "latitude": 29.58242,
            "longitude": -98.47071,
            "city_project_no": "23-01632",
            "scope": "Drainage improvements to six low water crossings to provide flood relief and emergency access during flood conditions to the Shady Oaks neighborhood and Bradley Middle School to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Winter 2021",
            "consultant": "Sanchez-Salazar & Associates, LLC",
            "contractor": null
        },
        {
            "project": "Port San Antonio",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Winter 2022",
            "bond_budget": 24000000,
            "bond_expenditures": 24000000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 28843743,
            "latitude": 29.37148,
            "longitude": -98.56666,
            "city_project_no": "23-01633",
            "scope": "Expand drainage infrastructure at Port San Antonio to provide adequate storm water capacity and reduce on-going flooding risks.",
            "design_start": "Winter 2017",
            "design_end": "Spring 2018",
            "consultant": "Pape-Dawson Engineers, Inc.",
            "contractor": null
        },
        {
            "project": "San Pedro Creek",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Winter 2022",
            "bond_budget": 14600000,
            "bond_expenditures": 14600000,
            "total_budget_sparse_field": 14600000,
            "total_expenditures": 14600000,
            "latitude": 29.42076,
            "longitude": -98.49726,
            "city_project_no": "23-01634",
            "scope": "Leverage local funding to support a improvements associated with the drainage components of Phase 1 and 2 of the San Pedro Creek Restoration Project.",
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": "Sundt Davila"
        },
        {
            "project": "Seeling Channel Phase 3",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2022",
            "bond_budget": 18000000,
            "bond_expenditures": 15341543,
            "total_budget_sparse_field": 0,
            "total_expenditures": 17307041,
            "latitude": 29.45805,
            "longitude": -98.54836,
            "city_project_no": "23-01635",
            "scope": "Continuation of multi-phase floodplain improvement project of Seeling Channel from Morning Glory to upstream of St. Cloud to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Unintech Consulting Engineers",
            "contractor": null
        },
        {
            "project": "South Pine Street\/Greer Street Phase 1",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Fall 2020",
            "bond_budget": 8000000,
            "bond_expenditures": 5520573,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6970178,
            "latitude": 29.38736,
            "longitude": -98.46959,
            "city_project_no": "23-01636",
            "scope": "Construction of a storm drain system in Highland Park area to provide flooding relief to neighborhood streets and properties.  This proposed phase includes curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Vickrey & Associates, Inc.",
            "contractor": null
        },
        {
            "project": "Upland Road",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Spring 2021",
            "bond_budget": 6910000,
            "bond_expenditures": 6568534,
            "total_budget_sparse_field": 8528338,
            "total_expenditures": 8528338,
            "latitude": 29.41582,
            "longitude": -98.40957,
            "city_project_no": "23-01637",
            "scope": "Construction of a storm drain system in the Eastwood Village area to provide ponding and erosion relief to the neighborhood streets and properties.  This proposed phase includes street reconstruction, curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Spring 2019",
            "consultant": "Ford Engineering, Inc.",
            "contractor": null
        },
        {
            "project": "Vance Jackson Road Low-Water Crossings",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Winter 2023",
            "bond_budget": 6357000,
            "bond_expenditures": 5593312,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7166988,
            "latitude": 29.54839,
            "longitude": -98.56626,
            "city_project_no": "23-01638",
            "scope": "Improve low water crossings along Vance Jackson Road at Orsinger Lane and south of Treehill Street to enhance safety and mobility.  This proposed phase includes street reconstruction, curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2020",
            "consultant": "M&S Engineering, LLC",
            "contractor": null
        },
        {
            "project": "West Military Drive & Westmar Drive Area",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Spring 2022",
            "bond_budget": 10160000,
            "bond_expenditures": 8139140,
            "total_budget_sparse_field": 11477339,
            "total_expenditures": 11477339,
            "latitude": 29.40969,
            "longitude": -98.63204,
            "city_project_no": "23-01639",
            "scope": "Construction of a storm drain system within Cable-Westwood\/Lackland Terrace area to provide flooding relief to neighborhood streets and properties to include curbs, sidewalks and driveway approaches as needed.",
            "design_start": "Spring 2018",
            "design_end": "Summer 2019",
            "consultant": "KFW Engineering",
            "contractor": null
        },
        {
            "project": "Public Art (Drainage)",
            "programme": "2017",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Summer 2021",
            "construction_end": "Fall 2025",
            "bond_budget": 1389000,
            "bond_expenditures": 1139122,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1338705,
            "latitude": 29.42634,
            "longitude": -98.50507,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Aquatic Center at Palo Alto College",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 0,
            "bond_expenditures": 0,
            "total_budget_sparse_field": 0,
            "total_expenditures": 0,
            "latitude": 29.32213,
            "longitude": -98.54923,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Beacon Hill Linear Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 300000,
            "bond_expenditures": 299687,
            "total_budget_sparse_field": 299687,
            "total_expenditures": 299687,
            "latitude": 29.46288,
            "longitude": -98.51148,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Beitel Creek Linear Trail Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2019",
            "construction_end": "Winter 2021",
            "bond_budget": 500000,
            "bond_expenditures": 497125,
            "total_budget_sparse_field": 497125,
            "total_expenditures": 497125,
            "latitude": 29.5372,
            "longitude": -98.39102,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Tezel Road City Facility",
            "programme": "2017",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2022",
            "construction_end": "Winter 2024",
            "bond_budget": 2500000,
            "bond_expenditures": 2500000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2975997,
            "latitude": 29.49507,
            "longitude": -98.66241,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brackenridge Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01,02",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2028",
            "bond_budget": 7750000,
            "bond_expenditures": 2411166,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4600435,
            "latitude": 29.46008,
            "longitude": -98.47228,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brackenridge Park\/Witte Museum Parking Garage Expansion",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Winter 2019",
            "bond_budget": 2000000,
            "bond_expenditures": 1980000,
            "total_budget_sparse_field": 2574097,
            "total_expenditures": 2574097,
            "latitude": 29.46062,
            "longitude": -98.46863,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Capitol Little League Baseball Fields",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Winter 2020",
            "bond_budget": 2000000,
            "bond_expenditures": 2000000,
            "total_budget_sparse_field": 2000000,
            "total_expenditures": 2000000,
            "latitude": 29.5483,
            "longitude": -98.41661,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Caracol Creek Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 400000,
            "bond_expenditures": 359754,
            "total_budget_sparse_field": 359754,
            "total_expenditures": 359754,
            "latitude": 29.43333,
            "longitude": -98.70946,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Classen-Steubing Ranch Park Property Acquisition & Development",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Spring 2023",
            "bond_budget": 9150000,
            "bond_expenditures": 9078628,
            "total_budget_sparse_field": 0,
            "total_expenditures": 11420277,
            "latitude": 29.6293,
            "longitude": -98.47575,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Comanche Lookout Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Winter 2021",
            "bond_budget": 400000,
            "bond_expenditures": 356606,
            "total_budget_sparse_field": 356606,
            "total_expenditures": 356606,
            "latitude": 29.58286,
            "longitude": -98.36986,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 1800000,
            "bond_expenditures": 293656,
            "total_budget_sparse_field": 0,
            "total_expenditures": 776836,
            "latitude": 29.30664,
            "longitude": -98.56341,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Copernicus Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Winter 2019",
            "bond_budget": 475000,
            "bond_expenditures": 461736,
            "total_budget_sparse_field": 461736,
            "total_expenditures": 461736,
            "latitude": 29.4143,
            "longitude": -98.39269,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Crystal Hills Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 250000,
            "bond_expenditures": 247415,
            "total_budget_sparse_field": 247415,
            "total_expenditures": 247415,
            "latitude": 29.48158,
            "longitude": -98.62227,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Cuellar Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 368000,
            "bond_expenditures": 356011,
            "total_budget_sparse_field": 0,
            "total_expenditures": 356011,
            "latitude": 29.42529,
            "longitude": -98.5716,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Culebra Creek Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 368000,
            "bond_expenditures": 316089,
            "total_budget_sparse_field": 316089,
            "total_expenditures": 316089,
            "latitude": 29.50486,
            "longitude": -98.71759,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Dawson Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2019",
            "construction_end": "Fall 2020",
            "bond_budget": 750000,
            "bond_expenditures": 750000,
            "total_budget_sparse_field": 750000,
            "total_expenditures": 750000,
            "latitude": 29.41922,
            "longitude": -98.45339,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 Heritage Community Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Summer 2023",
            "construction_end": "Fall 2024",
            "bond_budget": 8500000,
            "bond_expenditures": 9318594,
            "total_budget_sparse_field": 0,
            "total_expenditures": 14082642,
            "latitude": 29.41975,
            "longitude": -98.67905,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 5 Parks",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 1000000,
            "bond_expenditures": 989171,
            "total_budget_sparse_field": 989171,
            "total_expenditures": 989171,
            "latitude": 29.41093,
            "longitude": -98.53714,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 8 Park Land Acquisition & Development",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Spring 2023",
            "bond_budget": 500000,
            "bond_expenditures": 499990,
            "total_budget_sparse_field": 499990,
            "total_expenditures": 499990,
            "latitude": 29.57206,
            "longitude": -98.63103,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 9 Senior Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Summer 2022",
            "bond_budget": 13212000,
            "bond_expenditures": 12335989,
            "total_budget_sparse_field": 13869135,
            "total_expenditures": 13869135,
            "latitude": 29.55739,
            "longitude": -98.50008,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Downtown Parks",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Summer 2021",
            "bond_budget": 1250000,
            "bond_expenditures": 1239772,
            "total_budget_sparse_field": 1479772,
            "total_expenditures": 1479772,
            "latitude": 29.43028,
            "longitude": -98.49942,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Elmendorf Lake Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2018",
            "construction_end": "Fall 2019",
            "bond_budget": 2000000,
            "bond_expenditures": 2000000,
            "total_budget_sparse_field": 2000000,
            "total_expenditures": 2000000,
            "latitude": 29.42801,
            "longitude": -98.53961,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Fox Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Summer 2021",
            "construction_end": "Summer 2022",
            "bond_budget": 400000,
            "bond_expenditures": 392857,
            "total_budget_sparse_field": 0,
            "total_expenditures": 392857,
            "latitude": 29.57092,
            "longitude": -98.61906,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Friesenhahn Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 400000,
            "bond_expenditures": 387971,
            "total_budget_sparse_field": 387971,
            "total_expenditures": 387971,
            "latitude": 29.58482,
            "longitude": -98.39679,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Gilbert Garza Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 500000,
            "bond_expenditures": 484224,
            "total_budget_sparse_field": 0,
            "total_expenditures": 493364,
            "latitude": 29.45415,
            "longitude": -98.60018,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Gilbert Morgan Denman, Jr. Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 400000,
            "bond_expenditures": 400000,
            "total_budget_sparse_field": 400000,
            "total_expenditures": 400000,
            "latitude": 29.51026,
            "longitude": -98.5596,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hardberger Park (Parks)",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08,09",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Fall 2018",
            "construction_end": "Fall 2020",
            "bond_budget": 5500000,
            "bond_expenditures": 5499938,
            "total_budget_sparse_field": 5682263,
            "total_expenditures": 5682263,
            "latitude": 29.55839,
            "longitude": -98.52582,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Harlandale Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Summer 2019",
            "bond_budget": 350000,
            "bond_expenditures": 348976,
            "total_budget_sparse_field": 348976,
            "total_expenditures": 348976,
            "latitude": 29.35475,
            "longitude": -98.49431,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Harvey E. Najim YMCA  Phase 2",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 50000,
            "bond_expenditures": 49802,
            "total_budget_sparse_field": 49802,
            "total_expenditures": 49802,
            "latitude": 29.36594,
            "longitude": -98.47916,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Haskin Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Summer 2019",
            "bond_budget": 300000,
            "bond_expenditures": 296932,
            "total_budget_sparse_field": 296932,
            "total_expenditures": 296932,
            "latitude": 29.49764,
            "longitude": -98.44595,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hemisfair Civic Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Summer 2023",
            "bond_budget": 21000000,
            "bond_expenditures": 21000000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 31216140,
            "latitude": 29.42159,
            "longitude": -98.48689,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Jane Dubel Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 300000,
            "bond_expenditures": 300000,
            "total_budget_sparse_field": 392087,
            "total_expenditures": 392087,
            "latitude": 29.47595,
            "longitude": -98.59897,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Jupe Manor Neighborhood Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Spring 2021",
            "bond_budget": 1237000,
            "bond_expenditures": 1193694,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1237549,
            "latitude": 29.38956,
            "longitude": -98.39946,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Kingsborough Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 400000,
            "bond_expenditures": 382399,
            "total_budget_sparse_field": 382399,
            "total_expenditures": 382399,
            "latitude": 29.33113,
            "longitude": -98.49603,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lackland Terrace Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 300000,
            "bond_expenditures": 299996,
            "total_budget_sparse_field": 299996,
            "total_expenditures": 299996,
            "latitude": 29.41089,
            "longitude": -98.64385,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lincoln Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2018",
            "construction_end": "Winter 2020",
            "bond_budget": 1000000,
            "bond_expenditures": 1000000,
            "total_budget_sparse_field": 2000000,
            "total_expenditures": 2000000,
            "latitude": 29.42087,
            "longitude": -98.44485,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lockwood & Dignowity Parks",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2023",
            "bond_budget": 4098000,
            "bond_expenditures": 3913836,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5851717,
            "latitude": 29.42897,
            "longitude": -98.47242,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Martin Luther King Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2022",
            "bond_budget": 3650000,
            "bond_expenditures": 3649560,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3747413,
            "latitude": 29.41484,
            "longitude": -98.41727,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Martin Luther King Plaza",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 650000,
            "bond_expenditures": 640028,
            "total_budget_sparse_field": 680278,
            "total_expenditures": 680278,
            "latitude": 29.42494,
            "longitude": -98.46113,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "McAllister Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09,10",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 2000000,
            "bond_expenditures": 2000000,
            "total_budget_sparse_field": 2000000,
            "total_expenditures": 2000000,
            "latitude": 29.55568,
            "longitude": -98.44277,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Miller's Pond Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Summer 2020",
            "bond_budget": 370000,
            "bond_expenditures": 367466,
            "total_budget_sparse_field": 367466,
            "total_expenditures": 367466,
            "latitude": 29.34479,
            "longitude": -98.61948,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Mission Drive-In Marquee",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Fall 2018",
            "bond_budget": 600000,
            "bond_expenditures": 599886,
            "total_budget_sparse_field": 599886,
            "total_expenditures": 599886,
            "latitude": 29.36616,
            "longitude": -98.48042,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Monterrey Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 475000,
            "bond_expenditures": 473431,
            "total_budget_sparse_field": 723431,
            "total_expenditures": 723431,
            "latitude": 29.43387,
            "longitude": -98.57713,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Monticello Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2019",
            "construction_end": "Spring 2020",
            "bond_budget": 300000,
            "bond_expenditures": 297843,
            "total_budget_sparse_field": 297843,
            "total_expenditures": 297843,
            "latitude": 29.46652,
            "longitude": -98.53651,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Mud Creek Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 400000,
            "bond_expenditures": 387927,
            "total_budget_sparse_field": 0,
            "total_expenditures": 390992,
            "latitude": 29.59595,
            "longitude": -98.44315,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Nani Falcone Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 250000,
            "bond_expenditures": 245375,
            "total_budget_sparse_field": 245375,
            "total_expenditures": 245375,
            "latitude": 29.52419,
            "longitude": -98.64396,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Natatorium at Soutwest ISD",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Summer 2022",
            "bond_budget": 4000000,
            "bond_expenditures": 4000000,
            "total_budget_sparse_field": 4000000,
            "total_expenditures": 4000000,
            "latitude": 29.30843,
            "longitude": -98.67314,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Territories Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2018",
            "construction_end": "Summer 2019",
            "bond_budget": 368000,
            "bond_expenditures": 368000,
            "total_budget_sparse_field": 368000,
            "total_expenditures": 368000,
            "latitude": 29.51806,
            "longitude": -98.6719,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Normoyle Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 1150000,
            "bond_expenditures": 1132297,
            "total_budget_sparse_field": 1132297,
            "total_expenditures": 1132297,
            "latitude": 29.38039,
            "longitude": -98.54028,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "North San Antonio Hills Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 532000,
            "bond_expenditures": 512875,
            "total_budget_sparse_field": 512875,
            "total_expenditures": 512875,
            "latitude": 29.46762,
            "longitude": -98.72353,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "O.P. Schnabel Park & Land Acquisition",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Fall 2019",
            "bond_budget": 7364000,
            "bond_expenditures": 7364000,
            "total_budget_sparse_field": 7364000,
            "total_expenditures": 7364000,
            "latitude": 29.5358,
            "longitude": -98.64276,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "O.P. Schnabel Park Multi-Generational Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 11000,
            "bond_expenditures": 0,
            "total_budget_sparse_field": 0,
            "total_expenditures": 0,
            "latitude": 29.53405,
            "longitude": -98.64211,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Old Spanish Trails Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01,07",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Winter 2019",
            "construction_end": "Summer 2020",
            "bond_budget": 3075000,
            "bond_expenditures": 3075000,
            "total_budget_sparse_field": 3245000,
            "total_expenditures": 3245000,
            "latitude": 29.47979,
            "longitude": -98.54082,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Oscar Perez Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Summer 2021",
            "bond_budget": 368000,
            "bond_expenditures": 367211,
            "total_budget_sparse_field": 367211,
            "total_expenditures": 367211,
            "latitude": 29.48174,
            "longitude": -98.65675,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Palo Alto Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Spring 2020",
            "bond_budget": 400000,
            "bond_expenditures": 400000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 555839,
            "latitude": 29.33589,
            "longitude": -98.55333,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Pearsall Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Spring 2022",
            "bond_budget": 3000000,
            "bond_expenditures": 2791819,
            "total_budget_sparse_field": 3791819,
            "total_expenditures": 3791819,
            "latitude": 29.35321,
            "longitude": -98.59439,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Perrin Homestead Historic Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Fall 2025",
            "bond_budget": 1000000,
            "bond_expenditures": 750188,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2608218,
            "latitude": 29.52502,
            "longitude": -98.41351,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Piper's Meadow Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Summer 2021",
            "bond_budget": 520000,
            "bond_expenditures": 511977,
            "total_budget_sparse_field": 511977,
            "total_expenditures": 511977,
            "latitude": 29.46505,
            "longitude": -98.63546,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Pittman-Sullivan Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2021",
            "construction_end": "Fall 2022",
            "bond_budget": 1550000,
            "bond_expenditures": 1523406,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1525182,
            "latitude": 29.41305,
            "longitude": -98.46364,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rainbow Hills Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2019",
            "construction_end": "Winter 2020",
            "bond_budget": 600000,
            "bond_expenditures": 480667,
            "total_budget_sparse_field": 480667,
            "total_expenditures": 480667,
            "latitude": 29.40486,
            "longitude": -98.66197,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Raintree Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 400000,
            "bond_expenditures": 371092,
            "total_budget_sparse_field": 371092,
            "total_expenditures": 371092,
            "latitude": 29.5801,
            "longitude": -98.35372,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rosedale Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Spring 2020",
            "bond_budget": 500000,
            "bond_expenditures": 496751,
            "total_budget_sparse_field": 572822,
            "total_expenditures": 572822,
            "latitude": 29.43569,
            "longitude": -98.55021,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Antonio Botanical Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2018",
            "construction_end": "Winter 2020",
            "bond_budget": 6050000,
            "bond_expenditures": 5985796,
            "total_budget_sparse_field": 5985796,
            "total_expenditures": 5985796,
            "latitude": 29.45872,
            "longitude": -98.45809,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Pedro Creek (Linear Park)",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2018",
            "construction_end": "Fall 2021",
            "bond_budget": 4900000,
            "bond_expenditures": 4900000,
            "total_budget_sparse_field": 4900000,
            "total_expenditures": 4900000,
            "latitude": 29.42707,
            "longitude": -98.49639,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Pedro Springs Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Fall 2021",
            "bond_budget": 1800000,
            "bond_expenditures": 1766247,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2028067,
            "latitude": 29.44792,
            "longitude": -98.50163,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Southside Lions Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 600000,
            "bond_expenditures": 600000,
            "total_budget_sparse_field": 826691,
            "total_expenditures": 826691,
            "latitude": 29.38435,
            "longitude": -98.43443,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Spicewood Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 300000,
            "bond_expenditures": 280319,
            "total_budget_sparse_field": 280319,
            "total_expenditures": 280319,
            "latitude": 29.30753,
            "longitude": -98.562,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Sports Education Facility",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 2000,
            "bond_expenditures": 1854,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1854,
            "latitude": 29.41488,
            "longitude": -98.39556,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Sports Facilities near Potranco Branch Library",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2018",
            "construction_end": "Winter 2019",
            "bond_budget": 2000000,
            "bond_expenditures": 2000000,
            "total_budget_sparse_field": 2000000,
            "total_expenditures": 2000000,
            "latitude": 29.44391,
            "longitude": -98.65892,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Stablewood Farms Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Winter 2020",
            "bond_budget": 400000,
            "bond_expenditures": 386161,
            "total_budget_sparse_field": 386161,
            "total_expenditures": 386161,
            "latitude": 29.3929,
            "longitude": -98.64974,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Stinson Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2019",
            "construction_end": "Spring 2019",
            "bond_budget": 400000,
            "bond_expenditures": 396866,
            "total_budget_sparse_field": 396866,
            "total_expenditures": 396866,
            "latitude": 29.34341,
            "longitude": -98.48475,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "The Alamo Area Plaza",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Summer 2026",
            "bond_budget": 7300000,
            "bond_expenditures": 7045278,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7266613,
            "latitude": 29.42569,
            "longitude": -98.48612,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Tom Slick Creek Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 368000,
            "bond_expenditures": 367134,
            "total_budget_sparse_field": 367134,
            "total_expenditures": 367134,
            "latitude": 29.431,
            "longitude": -98.63418,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Central Library",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2023",
            "bond_budget": 3000000,
            "bond_expenditures": 3000000,
            "total_budget_sparse_field": 3340000,
            "total_expenditures": 3340000,
            "latitude": 29.43203,
            "longitude": -98.49251,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "UTSA Athletics Complex",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Spring 2021",
            "bond_budget": 10000000,
            "bond_expenditures": 9929935,
            "total_budget_sparse_field": 9929935,
            "total_expenditures": 9929935,
            "latitude": 29.57366,
            "longitude": -98.64484,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Villa Coronado Park",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 300000,
            "bond_expenditures": 298343,
            "total_budget_sparse_field": 298343,
            "total_expenditures": 298343,
            "latitude": 29.31414,
            "longitude": -98.47074,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Wheatley Heights Sports Complex",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Fall 2023",
            "bond_budget": 3000000,
            "bond_expenditures": 3000000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3198946,
            "latitude": 29.41938,
            "longitude": -98.41881,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Woodlawn Lake Park Multi-Generational Center",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2021",
            "construction_end": "Fall 2022",
            "bond_budget": 5000000,
            "bond_expenditures": 4981114,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6559733,
            "latitude": 29.45271,
            "longitude": -98.53423,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "World Heritage Park & Land Acquisition",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Fall 2024",
            "bond_budget": 3713000,
            "bond_expenditures": 3679940,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3705983,
            "latitude": 29.38886,
            "longitude": -98.49694,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Zoo Parking Garage",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2018",
            "construction_end": "Fall 2019",
            "bond_budget": 11750000,
            "bond_expenditures": 11750000,
            "total_budget_sparse_field": 12328590,
            "total_expenditures": 12328590,
            "latitude": 29.46391,
            "longitude": -98.47618,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Parks, Recreation & Open Space)",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Fall 2019",
            "construction_end": "Summer 2022",
            "bond_budget": 1872000,
            "bond_expenditures": 1701668,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1744584,
            "latitude": 29.42327,
            "longitude": -98.48742,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Forest Hills Branch Library",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2020",
            "construction_end": "Winter 2021",
            "bond_budget": 900000,
            "bond_expenditures": 900000,
            "total_budget_sparse_field": 1093221,
            "total_expenditures": 1093221,
            "latitude": 29.46413,
            "longitude": -98.58884,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Greater Love Multi-Generational Cultural\/Community Center",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Fall 2023",
            "bond_budget": 2000000,
            "bond_expenditures": 2000000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3540812,
            "latitude": 29.40116,
            "longitude": -98.4394,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Guadalupe Cultural Arts Center",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2020",
            "construction_end": "Summer 2020",
            "bond_budget": 450000,
            "bond_expenditures": 447140,
            "total_budget_sparse_field": 447140,
            "total_expenditures": 447140,
            "latitude": 29.42136,
            "longitude": -98.5271,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Las Palmas Branch Library",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2022",
            "construction_end": "Winter 2024",
            "bond_budget": 1700000,
            "bond_expenditures": 1700000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1916339,
            "latitude": 29.41817,
            "longitude": -98.54955,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Market Square",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2020",
            "construction_end": "Fall 2020",
            "bond_budget": 735000,
            "bond_expenditures": 713668,
            "total_budget_sparse_field": 713668,
            "total_expenditures": 713668,
            "latitude": 29.42516,
            "longitude": -98.49923,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "McCreless Branch Library",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2020",
            "construction_end": "Winter 2022",
            "bond_budget": 2500000,
            "bond_expenditures": 2500000,
            "total_budget_sparse_field": 3051212,
            "total_expenditures": 3051212,
            "latitude": 29.38146,
            "longitude": -98.45797,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Memorial Branch Library",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2021",
            "construction_end": "Fall 2022",
            "bond_budget": 3300000,
            "bond_expenditures": 3300000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3863735,
            "latitude": 29.44826,
            "longitude": -98.56206,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "The Neighborhood Place Cultural\/Community Center",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2017",
            "construction_end": "Summer 2019",
            "bond_budget": 1500000,
            "bond_expenditures": 1500000,
            "total_budget_sparse_field": 1500000,
            "total_expenditures": 1500000,
            "latitude": 29.44231,
            "longitude": -98.55609,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "World Heritage",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Fall 2024",
            "bond_budget": 5000000,
            "bond_expenditures": 4773872,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7265566,
            "latitude": 29.36594,
            "longitude": -98.47916,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "ZerNona Black Multi-Generational Cultural\/Community Center",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Fall 2024",
            "bond_budget": 2000000,
            "bond_expenditures": 2564637,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5595000,
            "latitude": 29.41358,
            "longitude": -98.47307,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Library & Cultural Facilities)",
            "programme": "2017",
            "proposition": "Library",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Winter 2021",
            "construction_end": "Fall 2024",
            "bond_budget": 240000,
            "bond_expenditures": 219076,
            "total_budget_sparse_field": 0,
            "total_expenditures": 239837,
            "latitude": 29.40116,
            "longitude": -98.4394,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Battered Women & Children\u2019s Shelter",
            "programme": "2017",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2017",
            "construction_end": "Fall 2019",
            "bond_budget": 1000000,
            "bond_expenditures": 1000000,
            "total_budget_sparse_field": 1000000,
            "total_expenditures": 1000000,
            "latitude": 29.50566,
            "longitude": -98.46657,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Fire Station #24 Replacement",
            "programme": "2017",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02,10",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Winter 2021",
            "construction_end": "Winter 2023",
            "bond_budget": 10000000,
            "bond_expenditures": 9512678,
            "total_budget_sparse_field": 0,
            "total_expenditures": 9771773,
            "latitude": 29.50097,
            "longitude": -98.41938,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Antonio Police Department Substation and Park Police Headquarters",
            "programme": "2017",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2024",
            "bond_budget": 20567000,
            "bond_expenditures": 20567000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 26310038,
            "latitude": 29.44519,
            "longitude": -98.48595,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Public Safety Facilities Improvements)",
            "programme": "2017",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Winter 2022",
            "construction_end": "Winter 2025",
            "bond_budget": 344000,
            "bond_expenditures": 192456,
            "total_budget_sparse_field": 0,
            "total_expenditures": 324624,
            "latitude": 29.4449,
            "longitude": -98.48598,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Neighborhood Improvements",
            "programme": "2017",
            "proposition": "Neighborhood",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Spring 2020",
            "construction_end": "Winter 2026",
            "bond_budget": 20000000,
            "bond_expenditures": 20514753,
            "total_budget_sparse_field": 0,
            "total_expenditures": 23383943,
            "latitude": 29.43005,
            "longitude": -98.50342,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Babcock Road (West Hausman to UTSA Boulevard)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 10000000,
            "bond_expenditures": 1730922,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3886824,
            "latitude": 29.5746,
            "longitude": -98.63167,
            "city_project_no": "23-03865",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Braun Road Sidewalks (Tezel Road to Northwest Loop 1604)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Spring 2027",
            "bond_budget": 3000000,
            "bond_expenditures": 724597,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1133579,
            "latitude": 29.53168,
            "longitude": -98.6701,
            "city_project_no": "23-03866",
            "scope": "Construct a shared-use path on northside of Braun Road from Tezel Road to Northwest Loop 1604 within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Bulverde Rd (Green Spring Dr -Redland Rd)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Summer 2028",
            "bond_budget": 13000000,
            "bond_expenditures": 1299643,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1461092,
            "latitude": 29.58835,
            "longitude": -98.42359,
            "city_project_no": "23-03867",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding. This is a multi-phased project.",
            "design_start": "Summer 2022",
            "design_end": "Summer 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Bynum Ave Ph2 (W Mayfield Blvd-W Gerald Av)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Summer 2024",
            "bond_budget": 5000000,
            "bond_expenditures": 3996380,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5047617,
            "latitude": 29.36567,
            "longitude": -98.56097,
            "city_project_no": "23-03868",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, bicycle facilities, drainage, traffic improvements, and other improvements as applicable and within available funding. This is a multi-phased project.",
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Citywide Bicycle Facilities",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Winter 2026",
            "construction_end": "Spring 2029",
            "bond_budget": 10000000,
            "bond_expenditures": 496877,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2295328,
            "latitude": 29.535,
            "longitude": -98.63863,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Citywide Bridge Improvements",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Fall 2023",
            "construction_end": "Summer 2025",
            "bond_budget": 1157000,
            "bond_expenditures": 1112279,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4866192,
            "latitude": 29.4625,
            "longitude": -98.52435,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Classen Rd (Classen Spur - Knollcreek Dr)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Spring 2028",
            "bond_budget": 10000000,
            "bond_expenditures": 2022022,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2305009,
            "latitude": 29.59269,
            "longitude": -98.40885,
            "city_project_no": "23-03871",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Summer 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Covel Rd (Ray Ellison - Old Pearsall)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 10000000,
            "bond_expenditures": 1181896,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3607336,
            "latitude": 29.35361,
            "longitude": -98.64638,
            "city_project_no": "23-03872",
            "scope": "Construct roadway improvements to include driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Summer 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Culebra Park (Area Streets)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 7000000,
            "bond_expenditures": 1013364,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1284671,
            "latitude": 29.45525,
            "longitude": -98.58993,
            "city_project_no": "23-03873",
            "scope": "Construct area roadways to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Culebra Road (IH-10 to Callaghan Road)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "01,05,07",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 18000000,
            "bond_expenditures": 2131000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3079282,
            "latitude": 29.44841,
            "longitude": -98.55869,
            "city_project_no": "23-03874",
            "scope": "Construct pedestrian safety improvements to include roadway, sidewalks, curbs, driveways approaches, bicycle facilities, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 1 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 11495000,
            "bond_expenditures": 7720601,
            "total_budget_sparse_field": 0,
            "total_expenditures": 9981131,
            "latitude": 29.48244,
            "longitude": -98.50785,
            "city_project_no": "23-03875",
            "scope": "Construct intersection improvements at Bitters Road at Ashton Village Drive - Cutter Green Drive and Bitters Road at Inwood Cove Drive and Rogers Wood to include turn lanes, curbs, sidewalks, driveway approaches, drainage, and traffic improvements as appl",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 1 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 803906,
            "total_budget_sparse_field": 0,
            "total_expenditures": 835545,
            "latitude": 29.47584,
            "longitude": -98.50492,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 2 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 11980000,
            "bond_expenditures": 8836313,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10111896,
            "latitude": 29.46655,
            "longitude": -98.40381,
            "city_project_no": "23-03877",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 2 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Winter 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 18169,
            "total_budget_sparse_field": 0,
            "total_expenditures": 204409,
            "latitude": 29.45226,
            "longitude": -98.41721,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 3 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 11212000,
            "bond_expenditures": 7866651,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8777998,
            "latitude": 29.35361,
            "longitude": -98.42497,
            "city_project_no": "23-03879",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 3 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Fall 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 438305,
            "total_budget_sparse_field": 0,
            "total_expenditures": 680523,
            "latitude": 29.31579,
            "longitude": -98.49258,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 9709000,
            "bond_expenditures": 7880964,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8570131,
            "latitude": 29.35505,
            "longitude": -98.61771,
            "city_project_no": "23-03881",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2022",
            "construction_end": "Winter 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 764284,
            "total_budget_sparse_field": 0,
            "total_expenditures": 785142,
            "latitude": 29.34078,
            "longitude": -98.60168,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 5 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 10520000,
            "bond_expenditures": 6652817,
            "total_budget_sparse_field": 0,
            "total_expenditures": 9096603,
            "latitude": 29.41091,
            "longitude": -98.52457,
            "city_project_no": "23-03883",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 5 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Spring 2026",
            "bond_budget": 3000000,
            "bond_expenditures": 1829530,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2810961,
            "latitude": 29.40676,
            "longitude": -98.53693,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 6 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Winter 2026",
            "bond_budget": 8918000,
            "bond_expenditures": 5364315,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5403945,
            "latitude": 29.46454,
            "longitude": -98.62489,
            "city_project_no": "23-03885",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 6 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Summer 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 362688,
            "total_budget_sparse_field": 0,
            "total_expenditures": 408802,
            "latitude": 29.48766,
            "longitude": -98.68814,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 9941000,
            "bond_expenditures": 3072039,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3401784,
            "latitude": 29.48477,
            "longitude": -98.59265,
            "city_project_no": "23-03888",
            "scope": "Construct pedestrian mobility improvement projects as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 Neighborhood Sidewalk Improve",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Winter 2027",
            "bond_budget": 16000000,
            "bond_expenditures": 1038157,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1658770,
            "latitude": 29.47329,
            "longitude": -98.59556,
            "city_project_no": "23-03889",
            "scope": "Construct sidewalk improvements including curbs and driveway approaches as applicable and within available funding.",
            "design_start": "Winter 2024",
            "design_end": "Summer 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 261482,
            "total_budget_sparse_field": 0,
            "total_expenditures": 818749,
            "latitude": 29.47271,
            "longitude": -98.56754,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 8 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2026",
            "bond_budget": 7640000,
            "bond_expenditures": 3351078,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4960061,
            "latitude": 29.5417,
            "longitude": -98.60951,
            "city_project_no": "23-03891",
            "scope": "Construct pedestrian mobility improvement projects as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Spring 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 8 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Fall 2023",
            "construction_end": "Summer 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 474789,
            "total_budget_sparse_field": 0,
            "total_expenditures": 503732,
            "latitude": 29.58401,
            "longitude": -98.60794,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 9 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Winter 2026",
            "bond_budget": 7344000,
            "bond_expenditures": 3541430,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3572225,
            "latitude": 29.57462,
            "longitude": -98.49605,
            "city_project_no": "23-03893",
            "scope": "Construct sidewalk improvements including curbs and driveway approaches as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 9 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 202396,
            "total_budget_sparse_field": 0,
            "total_expenditures": 662473,
            "latitude": 29.55715,
            "longitude": -98.49956,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "D9 Traffic & Mobility Imprv (Bitters Area)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Fall 2027",
            "bond_budget": 4000000,
            "bond_expenditures": 953153,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1337141,
            "latitude": 29.5951,
            "longitude": -98.53338,
            "city_project_no": "23-03895",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "D9 Traffic & Mobility Imprv (Stone Oak Area)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Winter 2028",
            "bond_budget": 5000000,
            "bond_expenditures": 954593,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2827056,
            "latitude": 29.6421,
            "longitude": -98.48941,
            "city_project_no": "23-03896",
            "scope": "Construct pedestrian mobility improvement projects as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 10 F-Streets Reconstruction",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2027",
            "bond_budget": 11741000,
            "bond_expenditures": 6668038,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7353231,
            "latitude": 29.54344,
            "longitude": -98.41683,
            "city_project_no": "23-03897",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 10 Pedestrian Mobility",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Summer 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 180727,
            "total_budget_sparse_field": 0,
            "total_expenditures": 667153,
            "latitude": 29.57198,
            "longitude": -98.40309,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Dorsey Dr (Moursund Blvd to Garnett Ave)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 5000000,
            "bond_expenditures": 761634,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1040477,
            "latitude": 29.33461,
            "longitude": -98.50732,
            "city_project_no": "23-03899",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Eastside Area Streets",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Summer 2028",
            "bond_budget": 6850000,
            "bond_expenditures": 1027242,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1276295,
            "latitude": 29.43139,
            "longitude": -98.47881,
            "city_project_no": "23-03900",
            "scope": "Construct area roadway improvements to include bicycle facilities, sidewalks, lighting, streetscape for multimodal connections to eastside parks, and other improvements as applicable and within available funding. Roadways may include: McCullough Avenue, B",
            "design_start": "Summer 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Evans Rd Ph1 (E Elm Creek - Masonwood)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 8850000,
            "bond_expenditures": 1108408,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1740925,
            "latitude": 29.64689,
            "longitude": -98.43285,
            "city_project_no": "23-03901",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Floyd Curl Drive (Huebner Road to Charles Katz)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2024",
            "construction_end": "Spring 2025",
            "bond_budget": 12000000,
            "bond_expenditures": 6835101,
            "total_budget_sparse_field": 0,
            "total_expenditures": 10041521,
            "latitude": 29.52118,
            "longitude": -98.58967,
            "city_project_no": "23-03902",
            "scope": "Construct roadway improvements to include curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Summer 2022",
            "design_end": "Spring 2023",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Gardendale Str(Wurzbach Rd - Bluemel Rd)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 3000000,
            "bond_expenditures": 500985,
            "total_budget_sparse_field": 0,
            "total_expenditures": 659904,
            "latitude": 29.52614,
            "longitude": -98.5711,
            "city_project_no": "23-03903",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Spring 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hemisfair Boulevard Phase 3",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 9000000,
            "bond_expenditures": 256192,
            "total_budget_sparse_field": 0,
            "total_expenditures": 286010,
            "latitude": 29.41842,
            "longitude": -98.48269,
            "city_project_no": "23-03904",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.  This is a multi-phased project.",
            "design_start": "Fall 2023",
            "design_end": "Summer 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "JonesMaltsbrger (Autry Pond-Redland) Design",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 1000000,
            "bond_expenditures": 890909,
            "total_budget_sparse_field": 0,
            "total_expenditures": 891940,
            "latitude": 29.59796,
            "longitude": -98.42823,
            "city_project_no": "23-03905",
            "scope": "Complete preliminary project development which may include schematic design and plans for  roadway and associated improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Marbach Area Streets (Loop 410 -Horal Dr)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "04,06",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2027",
            "construction_end": "Summer 2029",
            "bond_budget": 15000000,
            "bond_expenditures": 1012301,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1583444,
            "latitude": 29.41782,
            "longitude": -98.6496,
            "city_project_no": "23-03906",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Spring 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Military Drive (Sequoia Height to East of Reed Road)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Spring 2027",
            "bond_budget": 11500000,
            "bond_expenditures": 1323056,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5626933,
            "latitude": 29.45934,
            "longitude": -98.66512,
            "city_project_no": "23-03907",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "N New Braunfels Ph2 (E Houston-Paso Hondo)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 6500000,
            "bond_expenditures": 3461941,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4880354,
            "latitude": 29.4231,
            "longitude": -98.46127,
            "city_project_no": "23-03908",
            "scope": "Construct roadway improvements to include sidewalks, driveway approaches, drainage and other improvements as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Spring 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Oak Haven Area Streets (Kentwood Phase2)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 7900000,
            "bond_expenditures": 890526,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1268942,
            "latitude": 29.59718,
            "longitude": -98.4626,
            "city_project_no": "23-03909",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Old Hwy 90 Ph2 (StateHwy151-USHwy90 W)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2028",
            "construction_end": "Spring 2030",
            "bond_budget": 8100000,
            "bond_expenditures": 3665356,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4064683,
            "latitude": 29.41516,
            "longitude": -98.59994,
            "city_project_no": "23-03910",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding. This is a multi-phased project.",
            "design_start": "Spring 2023",
            "design_end": "Summer 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Perennial Area Str (HeimerRd-DutchMyrtle)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Spring 2027",
            "bond_budget": 2750000,
            "bond_expenditures": 375632,
            "total_budget_sparse_field": 0,
            "total_expenditures": 522135,
            "latitude": 29.56484,
            "longitude": -98.47595,
            "city_project_no": "23-03911",
            "scope": "Reconstruct area roadways, to include sidewalks, curbs, driveway approaches and other improvements as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Port San Antonio Area Streets",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Summer 2028",
            "bond_budget": 15000000,
            "bond_expenditures": 2285524,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2740764,
            "latitude": 29.3848,
            "longitude": -98.56559,
            "city_project_no": "23-03912",
            "scope": "Construct roadway improvements at Port San Antonio to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding. This is a multi-phased project.  Roadways may include: Billy Mitchell Bouleva",
            "design_start": "Summer 2022",
            "design_end": "Fall 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Probandt Street Phase 2",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2028",
            "construction_end": "Summer 2029",
            "bond_budget": 5000000,
            "bond_expenditures": 1478238,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2720518,
            "latitude": 29.40704,
            "longitude": -98.49551,
            "city_project_no": "23-03913",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, intersection improvements at South Alamo, and other improvements as applicable and within available funding.  This is a multi-phased project.",
            "design_start": "Summer 2018",
            "design_end": "Winter 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Streets)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2029",
            "bond_budget": 7050000,
            "bond_expenditures": 450638,
            "total_budget_sparse_field": 0,
            "total_expenditures": 731765,
            "latitude": 29.42458,
            "longitude": -98.49557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Toepperwein (Nacogdoches-Raintree Forest)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Fall 2028",
            "bond_budget": 14500000,
            "bond_expenditures": 2017281,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2376649,
            "latitude": 29.57741,
            "longitude": -98.36148,
            "city_project_no": "23-03922",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Roosevelt Ave (VFW Blvd to Harding Blvd)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2029",
            "construction_end": "Fall 2030",
            "bond_budget": 12000000,
            "bond_expenditures": 484347,
            "total_budget_sparse_field": 0,
            "total_expenditures": 979228,
            "latitude": 29.35914,
            "longitude": -98.48132,
            "city_project_no": "23-03915",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, bicycle facilities, drainage, traffic improvements, and other improvements as applicable and within available funding. This is a multi-phased project.",
            "design_start": "Summer 2023",
            "design_end": "Winter 2028",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Sidney Brooks (City Base Land-S New Braunfels)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 15000000,
            "bond_expenditures": 1646982,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3902765,
            "latitude": 29.34819,
            "longitude": -98.44035,
            "city_project_no": "23-03916",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle facilities, and other improvements as applicable and within available funding.  This is a multi-phased project.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Sonterra Rd Ext (Sonterra to Loop 1604)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Spring 2025",
            "bond_budget": 6000000,
            "bond_expenditures": 5011729,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5577517,
            "latitude": 29.60775,
            "longitude": -98.45746,
            "city_project_no": "23-03917",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2022",
            "design_end": "Summer 2023",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "S Brazos Str (Alazan Creek-Apache Creek)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 7500000,
            "bond_expenditures": 816121,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1579277,
            "latitude": 29.41979,
            "longitude": -98.5142,
            "city_project_no": "23-03918",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, bicycle facilities, drainage and traffic improvements as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "S Zarzamora Overpass at Union Pacific RR Ph2",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Winter 2029",
            "bond_budget": 2500000,
            "bond_expenditures": 1182872,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1263921,
            "latitude": 29.39535,
            "longitude": -98.53191,
            "city_project_no": "23-03919",
            "scope": "Facilitate construction of a railroad overpass on South Zarzamora within available funding.  This is a multi-phased project.",
            "design_start": "Summer 2018",
            "design_end": "Summer 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Southcross Boulevard Phase 2",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 5000000,
            "bond_expenditures": 1303087,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3412805,
            "latitude": 29.36877,
            "longitude": -98.4888,
            "city_project_no": "23-03920",
            "scope": "Construct pedestrian improvements to include sidewalks, curbs, driveway approaches, and other improvements as applicable and within available funding. This is a multi-phased project.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Texas A&M University Area Streets",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03,04",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2025",
            "construction_end": "Fall 2027",
            "bond_budget": 10600000,
            "bond_expenditures": 3862102,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8741821,
            "latitude": 29.2993,
            "longitude": -98.5307,
            "city_project_no": "23-03921",
            "scope": "Construct roadway improvements to include sidewalks, driveway approaches, drainage and other improvements as applicable and within available funding.  This project includes phased improvements to Perimeter Loop Road and a connector road to Mauermann Road.",
            "design_start": "Spring 2023",
            "design_end": "Summer 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Vance Jackson (Loop 410 to Adrian Drive)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 10000000,
            "bond_expenditures": 1172571,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1434177,
            "latitude": 29.50491,
            "longitude": -98.53509,
            "city_project_no": "23-03923",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, and traffic improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Summer 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Vance Jackson (Huebner to Wurzbach)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "08,01",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2027",
            "construction_end": "Spring 2029",
            "bond_budget": 16000000,
            "bond_expenditures": 2026015,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2494106,
            "latitude": 29.54558,
            "longitude": -98.56255,
            "city_project_no": "23-03924",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.  This is a multi-phased project.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Watson Rd Ph1 (Verano Pky at W Palo Alto)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2027",
            "construction_end": "Summer 2028",
            "bond_budget": 12000000,
            "bond_expenditures": 1479691,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1751467,
            "latitude": 29.28407,
            "longitude": -98.59611,
            "city_project_no": "23-03925",
            "scope": "Construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, bicycle infrastructure, and other improvements as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Wurzbach at Vance Jackson (Improvements)",
            "programme": "2022",
            "proposition": "Streets",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "08,01",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Winter 2024",
            "construction_end": "Fall 2027",
            "bond_budget": 6300000,
            "bond_expenditures": 1228202,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1239395,
            "latitude": 29.54045,
            "longitude": -98.5527,
            "city_project_no": "23-03926",
            "scope": "Construct intersection improvements at Wurzbach Road and Vance Jackson Road to include roadway widening and traffic signal upgrades as applicable and within available funding.",
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Barbara Drive Drainage Phase 3",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Spring 2028",
            "bond_budget": 6930000,
            "bond_expenditures": 1425837,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1915366,
            "latitude": 29.50614,
            "longitude": -98.4951,
            "city_project_no": "23-03927",
            "scope": "Construct the upgrade of an existing undersized storm drain system to include curbs, sidewalks and driveway approaches as applicable and within available funding.  This is a multi-phase project to relocate the floodplain away from structures.",
            "design_start": "Winter 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brookside Outfall (Esma Rdwy Area Ph2)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Spring 2028",
            "bond_budget": 4150000,
            "bond_expenditures": 1368495,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1942112,
            "latitude": 29.32734,
            "longitude": -98.43182,
            "city_project_no": "23-03928",
            "scope": "Construct channel improvements, culvert replacements and associated roadway reconstruction, curbs, and driveway approaches at culvert crossings as applicable and within available funding.  This is a  multi-phase and Hazard Mitigation Action Plan project.",
            "design_start": "Winter 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Eisenhauer-Northwood-Devonshire Ph IA",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 11150000,
            "bond_expenditures": 1317698,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4374074,
            "latitude": 29.49808,
            "longitude": -98.43936,
            "city_project_no": "23-03929",
            "scope": "Install an underground storm drain system and channel improvements to include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a multi-phase and Hazard Mitigation Action Plan",
            "design_start": "Winter 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Elmira Area Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2028",
            "construction_end": "Summer 2029",
            "bond_budget": 6050000,
            "bond_expenditures": 646125,
            "total_budget_sparse_field": 0,
            "total_expenditures": 669803,
            "latitude": 29.43219,
            "longitude": -98.4993,
            "city_project_no": "23-03930",
            "scope": "Install an underground storm drain system and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a Hazard Mitigation Action Plan project.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Evans Rd DrainPh1 (E Elm Creek-Masonwood)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 8450000,
            "bond_expenditures": 875182,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1335827,
            "latitude": 29.64689,
            "longitude": -98.43285,
            "city_project_no": "23-03931",
            "scope": "Install an underground storm drain system and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Fox Run Area Drain (FoxPeakDr & FoxCreek)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Spring 2027",
            "bond_budget": 1000000,
            "bond_expenditures": 169308,
            "total_budget_sparse_field": 0,
            "total_expenditures": 189895,
            "latitude": 29.58865,
            "longitude": -98.36531,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Frio City Road Outfall Phase 1",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Spring 2028",
            "bond_budget": 11300000,
            "bond_expenditures": 1485606,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2253861,
            "latitude": 29.40516,
            "longitude": -98.51735,
            "city_project_no": "23-03933",
            "scope": "Upgrade an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches, as applicable and within available funding.  This is a Hazard Mitigation Action Plan project.",
            "design_start": "Summer 2023",
            "design_end": "Summer 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Gardendale Drainage (Wurzbach-Bluemel)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 3360000,
            "bond_expenditures": 591629,
            "total_budget_sparse_field": 0,
            "total_expenditures": 780255,
            "latitude": 29.52614,
            "longitude": -98.5711,
            "city_project_no": "23-03934",
            "scope": "Install an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Spring 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "George Rd LWC (HuntersBow-NW MilitaryHwy)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 3700000,
            "bond_expenditures": 733617,
            "total_budget_sparse_field": 0,
            "total_expenditures": 849160,
            "latitude": 29.56212,
            "longitude": -98.54047,
            "city_project_no": "23-03935",
            "scope": "Construct low water crossing and associated improvements as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Spring 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lower French Creek Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "06,07",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Fall 2026",
            "construction_end": "Spring 2028",
            "bond_budget": 6500000,
            "bond_expenditures": 1303997,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1620689,
            "latitude": 29.489,
            "longitude": -98.63901,
            "city_project_no": "23-03936",
            "scope": "Construct improved low water crossings, driveway culverts, and channel improvements as applicable and within available funding.  This is a Hazard Mitigation Action Plan project to increase creek conveyance.",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Marbach Rd Area Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "04,06",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2027",
            "construction_end": "Summer 2029",
            "bond_budget": 15800000,
            "bond_expenditures": 941789,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1462011,
            "latitude": 29.41782,
            "longitude": -98.6496,
            "city_project_no": "23-03937",
            "scope": "Upgrade an undersized existing storm drain system which may include associated road reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a Hazard Mitigation Action Plan project.",
            "design_start": "Summer 2023",
            "design_end": "Spring 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "N New Braunfels (Austin Hwy-Larkwood) Design",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 1000000,
            "bond_expenditures": 669040,
            "total_budget_sparse_field": 0,
            "total_expenditures": 938135,
            "latitude": 29.49292,
            "longitude": -98.45931,
            "city_project_no": "23-03938",
            "scope": "Complete preliminary project development which may include schematic design and plans for drainage and associated improvements as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Spring 2027",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Oak Haven Area Drainage (Kentwood Ph 2)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 7900000,
            "bond_expenditures": 900566,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1139575,
            "latitude": 29.59718,
            "longitude": -98.4626,
            "city_project_no": "23-03939",
            "scope": "Install an underground storm drain system which may include associated reconstruction of the roadway, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Peggy Dr Area Drainage (Eastgate Subdivision)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 20000000,
            "bond_expenditures": 2614998,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3037759,
            "latitude": 29.43177,
            "longitude": -98.38495,
            "city_project_no": "23-03940",
            "scope": "Complete the regrading of an existing earthen channel and installation of an underground storm drain system and associated roadway reconstruction with curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Summer 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Perennial Drive Area Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Spring 2027",
            "bond_budget": 2750000,
            "bond_expenditures": 457092,
            "total_budget_sparse_field": 0,
            "total_expenditures": 629358,
            "latitude": 29.56484,
            "longitude": -98.47595,
            "city_project_no": "23-03941",
            "scope": "Install an underground storm drain system and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Summer 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Drainage)",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 2550000,
            "bond_expenditures": 217526,
            "total_budget_sparse_field": 0,
            "total_expenditures": 406959,
            "latitude": 29.42458,
            "longitude": -98.49557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Quentin Drive Alley Interim Improvements",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Winter 2025",
            "bond_budget": 973000,
            "bond_expenditures": 735622,
            "total_budget_sparse_field": 0,
            "total_expenditures": 903269,
            "latitude": 29.4693,
            "longitude": -98.53692,
            "city_project_no": "23-03943",
            "scope": "Reconstruct the alley and associated improvements between Leming Drive and Quentin Drive as applicable and within available funding.",
            "design_start": "Fall 2022",
            "design_end": "Summer 2023",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Seeling Drainage Phase 4",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 7880000,
            "bond_expenditures": 1646503,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3493990,
            "latitude": 29.46072,
            "longitude": -98.55298,
            "city_project_no": "23-03944",
            "scope": "Install an underground storm drain system and associated roadway reconstruction to include curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a multi-phase and Hazard Mitigation Action Plan project.",
            "design_start": "Winter 2023",
            "design_end": "Fall 2024",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "South Pine Roadway Drainage Phase 2",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Winter 2028",
            "bond_budget": 11000000,
            "bond_expenditures": 1629062,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1870788,
            "latitude": 29.39006,
            "longitude": -98.46542,
            "city_project_no": "23-03945",
            "scope": "Install an underground storm drain system and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a multi-phase project.",
            "design_start": "Spring 2023",
            "design_end": "Spring 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Southwell North Area Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 5930000,
            "bond_expenditures": 883220,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1152105,
            "latitude": 29.53992,
            "longitude": -98.59073,
            "city_project_no": "23-03946",
            "scope": "Install an underground storm drain system and an earthen channel outfall to include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.  This is a Hazard Mitigation Action Plan project.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Valley Hi Area Drain-Medina Base Ph1",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Spring 2028",
            "bond_budget": 5700000,
            "bond_expenditures": 1084610,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1298594,
            "latitude": 29.37511,
            "longitude": -98.64744,
            "city_project_no": "23-03947",
            "scope": "Install an underground storm drain system which may include improvements to two low water crossings, reconstruction of existing roadside earthen ditches and associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and wit",
            "design_start": "Spring 2023",
            "design_end": "Winter 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "W Broadview Dr & Oakwood Dr Drainage Ph1",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2027",
            "construction_end": "Summer 2028",
            "bond_budget": 10400000,
            "bond_expenditures": 1060504,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1957135,
            "latitude": 29.46754,
            "longitude": -98.57817,
            "city_project_no": "23-03948",
            "scope": "Install an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Wilcox Avenue Area Drainage",
            "programme": "2022",
            "proposition": "Drainage",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Summer 2028",
            "bond_budget": 15400000,
            "bond_expenditures": 1653697,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2035956,
            "latitude": 29.36815,
            "longitude": -98.55784,
            "city_project_no": "23-03949",
            "scope": "Install an underground storm drain system which may include associated roadway reconstruction, curbs, sidewalks, and driveway approaches as applicable and within available funding.",
            "design_start": "Spring 2023",
            "design_end": "Summer 2025",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Al Forge Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 500000,
            "bond_expenditures": 154447,
            "total_budget_sparse_field": 500000,
            "total_expenditures": 545164,
            "latitude": 29.36275,
            "longitude": -98.53965,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Arnold Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Spring 2024",
            "bond_budget": 500000,
            "bond_expenditures": 160407,
            "total_budget_sparse_field": 0,
            "total_expenditures": 276720,
            "latitude": 29.33188,
            "longitude": -98.53142,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Beacon Hill Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 500000,
            "bond_expenditures": 350053,
            "total_budget_sparse_field": 0,
            "total_expenditures": 563135,
            "latitude": 29.46327,
            "longitude": -98.51137,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Belmeade Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2023",
            "construction_end": "Spring 2024",
            "bond_budget": 300000,
            "bond_expenditures": 250490,
            "total_budget_sparse_field": 0,
            "total_expenditures": 250510,
            "latitude": 29.46411,
            "longitude": -98.44444,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Benavides Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 800000,
            "bond_expenditures": 815000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1267940,
            "latitude": 29.41081,
            "longitude": -98.53719,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brackenridge Park Facilities",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "01,02",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 5000000,
            "bond_expenditures": 36311,
            "total_budget_sparse_field": 0,
            "total_expenditures": 59527,
            "latitude": 29.46023,
            "longitude": -98.47314,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Brackenridge Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "01,02",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Winter 2027",
            "construction_end": "Fall 2028",
            "bond_budget": 2500000,
            "bond_expenditures": 326766,
            "total_budget_sparse_field": 0,
            "total_expenditures": 455809,
            "latitude": 29.461,
            "longitude": -98.47839,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Calderon Clubhouse (Boys & Girls Clubs of SA)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Fall 2025",
            "bond_budget": 3750000,
            "bond_expenditures": 3469338,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3667807,
            "latitude": 29.4235,
            "longitude": -98.5363,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Caracol Creek Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 500000,
            "bond_expenditures": 463982,
            "total_budget_sparse_field": 0,
            "total_expenditures": 466788,
            "latitude": 29.43288,
            "longitude": -98.70584,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Cassiano Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 3750000,
            "bond_expenditures": 371570,
            "total_budget_sparse_field": 0,
            "total_expenditures": 827662,
            "latitude": 29.4141,
            "longitude": -98.52971,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Cathedral Rock Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 500000,
            "bond_expenditures": 378972,
            "total_budget_sparse_field": 0,
            "total_expenditures": 495719,
            "latitude": 29.47514,
            "longitude": -98.64722,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Citywide Bicycle Recreational Facilities",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04,07,08",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 3250000,
            "bond_expenditures": 639433,
            "total_budget_sparse_field": 0,
            "total_expenditures": 812942,
            "latitude": 29.35321,
            "longitude": -98.59439,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Classen-Steubing Ranch Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 5000000,
            "bond_expenditures": 1609324,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2891705,
            "latitude": 29.62932,
            "longitude": -98.47262,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Comanche Lookout Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 1250000,
            "bond_expenditures": 288382,
            "total_budget_sparse_field": 0,
            "total_expenditures": 744483,
            "latitude": 29.58342,
            "longitude": -98.36926,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Concepcion Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 600000,
            "bond_expenditures": 349103,
            "total_budget_sparse_field": 0,
            "total_expenditures": 675627,
            "latitude": 29.38864,
            "longitude": -98.49708,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Cuellar Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Winter 2027",
            "bond_budget": 750000,
            "bond_expenditures": 187579,
            "total_budget_sparse_field": 0,
            "total_expenditures": 534247,
            "latitude": 29.42426,
            "longitude": -98.57126,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Dellview Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 500000,
            "bond_expenditures": 343701,
            "total_budget_sparse_field": 0,
            "total_expenditures": 517038,
            "latitude": 29.50386,
            "longitude": -98.54048,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 1 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Summer 2026",
            "bond_budget": 4000000,
            "bond_expenditures": 617969,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1643362,
            "latitude": 29.48965,
            "longitude": -98.51946,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 1 Parks &Multi Gen Rec Facility",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 8000000,
            "bond_expenditures": 729308,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1069641,
            "latitude": 29.44214,
            "longitude": -98.53115,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 2 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 1500000,
            "bond_expenditures": 822381,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1630640,
            "latitude": 29.40525,
            "longitude": -98.39909,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 3 Aquatics Facility",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 5000000,
            "bond_expenditures": 600073,
            "total_budget_sparse_field": 0,
            "total_expenditures": 738657,
            "latitude": 29.36635,
            "longitude": -98.47868,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 3 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Winter 2025",
            "bond_budget": 900000,
            "bond_expenditures": 440237,
            "total_budget_sparse_field": 0,
            "total_expenditures": 900000,
            "latitude": 29.399,
            "longitude": -98.45562,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 4 Multigenerational Recreational",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Cancelled",
            "current_status": "Cancelled",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 0,
            "bond_expenditures": 0,
            "total_budget_sparse_field": 0,
            "total_expenditures": 0,
            "latitude": 29.32437,
            "longitude": -98.54582,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 5 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Spring 2026",
            "bond_budget": 2175000,
            "bond_expenditures": 1191092,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2243763,
            "latitude": 29.38044,
            "longitude": -98.50988,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 Parks",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 900000,
            "bond_expenditures": 254704,
            "total_budget_sparse_field": 0,
            "total_expenditures": 354496,
            "latitude": 29.48044,
            "longitude": -98.62161,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "District 7 Parks Shade Enhancements",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2023",
            "construction_end": "Spring 2024",
            "bond_budget": 750000,
            "bond_expenditures": 749674,
            "total_budget_sparse_field": 0,
            "total_expenditures": 749816,
            "latitude": 29.48144,
            "longitude": -98.57478,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Eastside Clubhouse (Boys&GirlsClubsofSA)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2022",
            "construction_end": "Fall 2025",
            "bond_budget": 3750000,
            "bond_expenditures": 3202737,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3547832,
            "latitude": 29.41391,
            "longitude": -98.41982,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Eisenhower Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Fall 2026",
            "bond_budget": 800000,
            "bond_expenditures": 130537,
            "total_budget_sparse_field": 0,
            "total_expenditures": 152158,
            "latitude": 29.62223,
            "longitude": -98.58294,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Feather Ridge Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2023",
            "construction_end": "Winter 2024",
            "bond_budget": 250000,
            "bond_expenditures": 238569,
            "total_budget_sparse_field": 0,
            "total_expenditures": 238569,
            "latitude": 29.56063,
            "longitude": -98.36814,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Florida Street Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Fall 2024",
            "bond_budget": 250000,
            "bond_expenditures": 137899,
            "total_budget_sparse_field": 0,
            "total_expenditures": 212610,
            "latitude": 29.40801,
            "longitude": -98.48483,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Friedrich Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 800000,
            "bond_expenditures": 711931,
            "total_budget_sparse_field": 0,
            "total_expenditures": 763941,
            "latitude": 29.63527,
            "longitude": -98.63627,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Friesenhahn Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 800000,
            "bond_expenditures": 368609,
            "total_budget_sparse_field": 0,
            "total_expenditures": 593342,
            "latitude": 29.58373,
            "longitude": -98.39951,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Gilbert Garza Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 800000,
            "bond_expenditures": 149348,
            "total_budget_sparse_field": 0,
            "total_expenditures": 173970,
            "latitude": 29.45358,
            "longitude": -98.59865,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Greater Love Multigenerational & Rec Ctr",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2022",
            "construction_end": "Fall 2023",
            "bond_budget": 500000,
            "bond_expenditures": 499792,
            "total_budget_sparse_field": 0,
            "total_expenditures": 499792,
            "latitude": 29.40116,
            "longitude": -98.4394,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Harlandale Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 750000,
            "bond_expenditures": 216870,
            "total_budget_sparse_field": 0,
            "total_expenditures": 507825,
            "latitude": 29.35616,
            "longitude": -98.49538,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Hemisfair Civic Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2023",
            "construction_end": "Winter 2025",
            "bond_budget": 18000000,
            "bond_expenditures": 17870760,
            "total_budget_sparse_field": 0,
            "total_expenditures": 23015252,
            "latitude": 29.42159,
            "longitude": -98.48689,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Heritage Neighborhood Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Fall 2024",
            "bond_budget": 800000,
            "bond_expenditures": 309394,
            "total_budget_sparse_field": 0,
            "total_expenditures": 890000,
            "latitude": 29.41852,
            "longitude": -98.67909,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Jupe Manor Neighborhood Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Winter 2025",
            "bond_budget": 500000,
            "bond_expenditures": 250179,
            "total_budget_sparse_field": 0,
            "total_expenditures": 490159,
            "latitude": 29.38756,
            "longitude": -98.39667,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lady Bird Johnson Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 1250000,
            "bond_expenditures": 249446,
            "total_budget_sparse_field": 0,
            "total_expenditures": 344548,
            "latitude": 29.53412,
            "longitude": -98.42543,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lee's Creek Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 200000,
            "bond_expenditures": 284351,
            "total_budget_sparse_field": 0,
            "total_expenditures": 624523,
            "latitude": 29.47366,
            "longitude": -98.56385,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Lockwood\/Dignowity Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 155055,
            "total_budget_sparse_field": 0,
            "total_expenditures": 359881,
            "latitude": 29.42957,
            "longitude": -98.47252,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Martin Luther King Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 859879,
            "total_budget_sparse_field": 0,
            "total_expenditures": 992761,
            "latitude": 29.41364,
            "longitude": -98.41988,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Maverick Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2026",
            "bond_budget": 600000,
            "bond_expenditures": 155892,
            "total_budget_sparse_field": 0,
            "total_expenditures": 452604,
            "latitude": 29.43442,
            "longitude": -98.47972,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "McAllister Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "9,10",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Fall 2024",
            "construction_end": "Winter 2026",
            "bond_budget": 2000000,
            "bond_expenditures": 1800662,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2039666,
            "latitude": 29.55622,
            "longitude": -98.44696,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Medina River Natural Area",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Fall 2026",
            "bond_budget": 800000,
            "bond_expenditures": 172962,
            "total_budget_sparse_field": 0,
            "total_expenditures": 180705,
            "latitude": 29.26354,
            "longitude": -98.57966,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Millers Pond Park (Community Rec Ctr)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 800000,
            "bond_expenditures": 460672,
            "total_budget_sparse_field": 0,
            "total_expenditures": 786104,
            "latitude": 29.34548,
            "longitude": -98.61864,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Mitchell Lake Audubon Center",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 6000000,
            "bond_expenditures": 286228,
            "total_budget_sparse_field": 0,
            "total_expenditures": 588686,
            "latitude": 29.31095,
            "longitude": -98.49986,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Monterrey Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 800000,
            "bond_expenditures": 282817,
            "total_budget_sparse_field": 0,
            "total_expenditures": 861809,
            "latitude": 29.43491,
            "longitude": -98.57588,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Nani Falcone Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 750000,
            "bond_expenditures": 451109,
            "total_budget_sparse_field": 0,
            "total_expenditures": 710234,
            "latitude": 29.52309,
            "longitude": -98.64584,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Buchsenschutz Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "10",
            "district": 10,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 1000000,
            "bond_expenditures": 396290,
            "total_budget_sparse_field": 0,
            "total_expenditures": 727921,
            "latitude": 29.57869,
            "longitude": -98.40536,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New District 6 Park (near Cielo Vista)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "",
            "construction_end": "",
            "bond_budget": 500000,
            "bond_expenditures": 68388,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1051951,
            "latitude": 29.46208,
            "longitude": -98.61305,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Medical Center Area Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Summer 2027",
            "bond_budget": 3250000,
            "bond_expenditures": 127903,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1792943,
            "latitude": 29.52338,
            "longitude": -98.59576,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Park at Orr Drive and Suzette Avenue",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Winter 2026",
            "construction_end": "Fall 2026",
            "bond_budget": 500000,
            "bond_expenditures": 68104,
            "total_budget_sparse_field": 0,
            "total_expenditures": 220107,
            "latitude": 29.40888,
            "longitude": -98.62203,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Parks at Nopal Str & S Gevers Str",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 800000,
            "bond_expenditures": 252661,
            "total_budget_sparse_field": 0,
            "total_expenditures": 793728,
            "latitude": 29.38763,
            "longitude": -98.45625,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Regional Park Phase 1 (District 6)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2027",
            "construction_end": "Fall 2028",
            "bond_budget": 6920000,
            "bond_expenditures": 1227473,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1402334,
            "latitude": 29.41307,
            "longitude": -98.60184,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Regional Park Ph1 & Normoyle Park(D5)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Winter 2028",
            "construction_end": "Summer 2029",
            "bond_budget": 6750000,
            "bond_expenditures": 1636437,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2346518,
            "latitude": 29.38061,
            "longitude": -98.53476,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "North San Antonio Hills Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Fall 2024",
            "bond_budget": 200000,
            "bond_expenditures": 196962,
            "total_budget_sparse_field": 0,
            "total_expenditures": 196962,
            "latitude": 29.46762,
            "longitude": -98.72353,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "O.P. Schnabel Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Fall 2025",
            "bond_budget": 1675000,
            "bond_expenditures": 1229725,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1640538,
            "latitude": 29.53495,
            "longitude": -98.63797,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Olmos Basin Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 1250000,
            "bond_expenditures": 304351,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1023325,
            "latitude": 29.49345,
            "longitude": -98.49247,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Pearsall Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 1900000,
            "bond_expenditures": 411100,
            "total_budget_sparse_field": 0,
            "total_expenditures": 514346,
            "latitude": 29.35167,
            "longitude": -98.59327,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Pickleball Recreational Improvements",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 1500000,
            "bond_expenditures": 568038,
            "total_budget_sparse_field": 0,
            "total_expenditures": 859625,
            "latitude": 29.44761,
            "longitude": -98.50082,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Pickwell Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 500000,
            "bond_expenditures": 633141,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1374601,
            "latitude": 29.35817,
            "longitude": -98.42812,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Piper's Meadow Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 500000,
            "bond_expenditures": 220455,
            "total_budget_sparse_field": 0,
            "total_expenditures": 432643,
            "latitude": 29.46505,
            "longitude": -98.63543,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Parks)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Spring 2026",
            "construction_end": "Summer 2028",
            "bond_budget": 4070000,
            "bond_expenditures": 417651,
            "total_budget_sparse_field": 0,
            "total_expenditures": 741653,
            "latitude": 29.42458,
            "longitude": -98.49557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rosedale Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Fall 2024",
            "bond_budget": 375000,
            "bond_expenditures": 374602,
            "total_budget_sparse_field": 0,
            "total_expenditures": 377060,
            "latitude": 29.43639,
            "longitude": -98.54971,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Antonio Botanical Center",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "Off Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Winter 2024",
            "construction_end": "Winter 2026",
            "bond_budget": 2500000,
            "bond_expenditures": 2500000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8328698,
            "latitude": 29.45804,
            "longitude": -98.46041,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Antonio Zoo",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2022",
            "construction_end": "Fall 2025",
            "bond_budget": 10000000,
            "bond_expenditures": 10000000,
            "total_budget_sparse_field": 0,
            "total_expenditures": 19818597,
            "latitude": 29.46264,
            "longitude": -98.47461,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "San Pedro Springs Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2027",
            "construction_end": "Summer 2028",
            "bond_budget": 1500000,
            "bond_expenditures": 331808,
            "total_budget_sparse_field": 0,
            "total_expenditures": 469147,
            "latitude": 29.44703,
            "longitude": -98.5016,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Southside Lions Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 1250000,
            "bond_expenditures": 831080,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1131635,
            "latitude": 29.38568,
            "longitude": -98.4274,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Spring Time Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Summer 2025",
            "bond_budget": 750000,
            "bond_expenditures": 578474,
            "total_budget_sparse_field": 0,
            "total_expenditures": 782496,
            "latitude": 29.55275,
            "longitude": -98.61742,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Stinson Park (Five Diamonds Little League)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2024",
            "construction_end": "Winter 2024",
            "bond_budget": 500000,
            "bond_expenditures": 419306,
            "total_budget_sparse_field": 0,
            "total_expenditures": 475889,
            "latitude": 29.34356,
            "longitude": -98.48407,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Stone Oak Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Spring 2024",
            "construction_end": "Fall 2024",
            "bond_budget": 750000,
            "bond_expenditures": 353346,
            "total_budget_sparse_field": 0,
            "total_expenditures": 691927,
            "latitude": 29.64677,
            "longitude": -98.46879,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Theater of SA (San Pedro Springs Park)",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Summer 2025",
            "bond_budget": 1000000,
            "bond_expenditures": 830316,
            "total_budget_sparse_field": 0,
            "total_expenditures": 918899,
            "latitude": 29.44821,
            "longitude": -98.50246,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Timber Ridge Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Winter 2026",
            "bond_budget": 500000,
            "bond_expenditures": 221420,
            "total_budget_sparse_field": 0,
            "total_expenditures": 532606,
            "latitude": 29.46934,
            "longitude": -98.65418,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Tom Slick Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 750000,
            "bond_expenditures": 180411,
            "total_budget_sparse_field": 0,
            "total_expenditures": 688946,
            "latitude": 29.42927,
            "longitude": -98.6351,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "UTSA Athletics Facilities",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "08",
            "district": 8,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Summer 2026",
            "bond_budget": 5000000,
            "bond_expenditures": 3357,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4601235,
            "latitude": 29.5803,
            "longitude": -98.6259,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Walker Ranch Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "09",
            "district": 9,
            "district_kind": "single",
            "construction_start": "Fall 2024",
            "construction_end": "Winter 2025",
            "bond_budget": 500000,
            "bond_expenditures": 478181,
            "total_budget_sparse_field": 0,
            "total_expenditures": 480624,
            "latitude": 29.57966,
            "longitude": -98.46557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Wheatley Heights Sports Complex",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2023",
            "construction_end": "Spring 2024",
            "bond_budget": 1000000,
            "bond_expenditures": 190950,
            "total_budget_sparse_field": 0,
            "total_expenditures": 1197412,
            "latitude": 29.41943,
            "longitude": -98.41881,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Woodlawn Lake Park",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Summer 2026",
            "construction_end": "Spring 2027",
            "bond_budget": 2020000,
            "bond_expenditures": 327142,
            "total_budget_sparse_field": 0,
            "total_expenditures": 408514,
            "latitude": 29.45276,
            "longitude": -98.53394,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Carver Branch Library Renovation",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Summer 2025",
            "construction_end": "Winter 2027",
            "bond_budget": 12500000,
            "bond_expenditures": 2223003,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7649305,
            "latitude": 29.4201,
            "longitude": -98.43447,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Central Library Renovation",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2022",
            "construction_end": "Fall 2025",
            "bond_budget": 6700000,
            "bond_expenditures": 2054987,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6888361,
            "latitude": 29.43199,
            "longitude": -98.49276,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "City-Owned Cultural Facilities Imprvmnts",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01,05",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Summer 2024",
            "construction_end": "Fall 2027",
            "bond_budget": 6000000,
            "bond_expenditures": 3086247,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3961601,
            "latitude": 29.4238,
            "longitude": -98.49234,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Ella Austin Community Ctr Renovation",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "02",
            "district": 2,
            "district_kind": "single",
            "construction_start": "Fall 2024",
            "construction_end": "Spring 2027",
            "bond_budget": 11500000,
            "bond_expenditures": 2463961,
            "total_budget_sparse_field": 0,
            "total_expenditures": 5386719,
            "latitude": 29.43205,
            "longitude": -98.47103,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Las Palmas Branch Library Renovation",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Summer 2024",
            "construction_end": "Spring 2027",
            "bond_budget": 5250000,
            "bond_expenditures": 2060135,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4957814,
            "latitude": 29.41813,
            "longitude": -98.54959,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Magik Theater Renovation",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Spring 2026",
            "bond_budget": 2750000,
            "bond_expenditures": 585762,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3400745,
            "latitude": 29.42017,
            "longitude": -98.48773,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Libraries Facilities)",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Fall 2026",
            "construction_end": "Fall 2027",
            "bond_budget": 875000,
            "bond_expenditures": 93473,
            "total_budget_sparse_field": 0,
            "total_expenditures": 143163,
            "latitude": 29.42458,
            "longitude": -98.49557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Tower of Americas Improvements",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Spring 2025",
            "construction_end": "Fall 2026",
            "bond_budget": 10000000,
            "bond_expenditures": 4328660,
            "total_budget_sparse_field": 0,
            "total_expenditures": 7803442,
            "latitude": 29.4188,
            "longitude": -98.48446,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "World Heritage Center Ph 2 Improvements",
            "programme": "2022",
            "proposition": "Facility",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Winter 2023",
            "construction_end": "Summer 2025",
            "bond_budget": 3500000,
            "bond_expenditures": 2698768,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4685815,
            "latitude": 29.36619,
            "longitude": -98.48039,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Animal Care Facilities Improvements",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "06",
            "district": 6,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Fall 2027",
            "bond_budget": 17284000,
            "bond_expenditures": 1521421,
            "total_budget_sparse_field": 0,
            "total_expenditures": 4080747,
            "latitude": 29.41431,
            "longitude": -98.59141,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Citywide Public Health & Safety Facility",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "02,05,07",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Fall 2021",
            "construction_end": "Spring 2026",
            "bond_budget": 15825000,
            "bond_expenditures": 8415540,
            "total_budget_sparse_field": 0,
            "total_expenditures": 12296687,
            "latitude": 29.42654,
            "longitude": -98.52456,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Fire Station #10 Facility Replacement",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Pre-Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "01",
            "district": 1,
            "district_kind": "single",
            "construction_start": "Summer 2028",
            "construction_end": "Fall 2029",
            "bond_budget": 12500000,
            "bond_expenditures": 38564,
            "total_budget_sparse_field": 0,
            "total_expenditures": 317640,
            "latitude": 29.44555,
            "longitude": -98.52524,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Fire Station #33 Facility Replacement",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Design",
            "current_status": "On Schedule",
            "council_district_recorded": "05",
            "district": 5,
            "district_kind": "single",
            "construction_start": "Fall 2026",
            "construction_end": "Winter 2028",
            "bond_budget": 12500000,
            "bond_expenditures": 1497876,
            "total_budget_sparse_field": 0,
            "total_expenditures": 2024819,
            "latitude": 29.40961,
            "longitude": -98.57416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "New Police Substation",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "03",
            "district": 3,
            "district_kind": "single",
            "construction_start": "Fall 2025",
            "construction_end": "Spring 2027",
            "bond_budget": 19000000,
            "bond_expenditures": 3534701,
            "total_budget_sparse_field": 0,
            "total_expenditures": 8224441,
            "latitude": 29.3362,
            "longitude": -98.48334,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Public Art (Public Safety Facilities)",
            "programme": "2022",
            "proposition": "Safety",
            "phase": "Design",
            "current_status": "Off Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Spring 2027",
            "construction_end": "Spring 2028",
            "bond_budget": 1171000,
            "bond_expenditures": 113962,
            "total_budget_sparse_field": 0,
            "total_expenditures": 141190,
            "latitude": 29.42458,
            "longitude": -98.49557,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Home Owner Rehabilitation & Preservation",
            "programme": "2022",
            "proposition": "Housing",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Summer 2023",
            "construction_end": "Winter 2028",
            "bond_budget": 45000000,
            "bond_expenditures": 11423472,
            "total_budget_sparse_field": 0,
            "total_expenditures": 16376642,
            "latitude": 29.42625,
            "longitude": -98.49416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rental Acquisition, Rehab, & Preservation",
            "programme": "2022",
            "proposition": "Housing",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Summer 2023",
            "construction_end": "Winter 2029",
            "bond_budget": 40000000,
            "bond_expenditures": 10196606,
            "total_budget_sparse_field": 0,
            "total_expenditures": 19341371,
            "latitude": 29.42625,
            "longitude": -98.49416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Permanent Onsite Supportive Homeless Srv",
            "programme": "2022",
            "proposition": "Housing",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Summer 2023",
            "construction_end": "Summer 2027",
            "bond_budget": 25000000,
            "bond_expenditures": 16719933,
            "total_budget_sparse_field": 0,
            "total_expenditures": 18713562,
            "latitude": 29.42625,
            "longitude": -98.49416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Rental Housing Production & Acquisition",
            "programme": "2022",
            "proposition": "Housing",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Winter 2023",
            "construction_end": "Summer 2028",
            "bond_budget": 35000000,
            "bond_expenditures": 15172739,
            "total_budget_sparse_field": 0,
            "total_expenditures": 20801389,
            "latitude": 29.42625,
            "longitude": -98.49416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Homeownership Production",
            "programme": "2022",
            "proposition": "Housing",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "CW",
            "district": null,
            "district_kind": "citywide",
            "construction_start": "Fall 2023",
            "construction_end": "Fall 2026",
            "bond_budget": 5000000,
            "bond_expenditures": 5469730,
            "total_budget_sparse_field": 0,
            "total_expenditures": 6081409,
            "latitude": 29.42625,
            "longitude": -98.49416,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "O.P Schabel Park Entrance Renovation",
            "programme": "2017",
            "proposition": "Parks",
            "phase": "Complete",
            "current_status": "On Schedule",
            "council_district_recorded": "07",
            "district": 7,
            "district_kind": "single",
            "construction_start": "Fall 2022",
            "construction_end": "Summer 2023",
            "bond_budget": 489000,
            "bond_expenditures": 463826,
            "total_budget_sparse_field": 0,
            "total_expenditures": 463926,
            "latitude": 29.5323,
            "longitude": -98.64463,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Linear Greenway Trails",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "Off Schedule",
            "council_district_recorded": "01,02,03",
            "district": null,
            "district_kind": "multi",
            "construction_start": "Spring 2025",
            "construction_end": "Summer 2028",
            "bond_budget": 103530000,
            "bond_expenditures": 19768488,
            "total_budget_sparse_field": 0,
            "total_expenditures": 45682046,
            "latitude": 29.39596,
            "longitude": -98.56811,
            "city_project_no": "23-04053",
            "scope": "Acquire and preserve open space for the development of multi-use trails along San Antonio creekways, greenways and urban corridors within available funding.",
            "design_start": "Winter 2023",
            "design_end": "Fall 2026",
            "consultant": null,
            "contractor": null
        },
        {
            "project": "Aquatic & Multigenerational Center at Palo Alto College",
            "programme": "2022",
            "proposition": "Parks",
            "phase": "Construction",
            "current_status": "On Schedule",
            "council_district_recorded": "04",
            "district": 4,
            "district_kind": "single",
            "construction_start": "Winter 2025",
            "construction_end": "Winter 2027",
            "bond_budget": 15300000,
            "bond_expenditures": 0,
            "total_budget_sparse_field": 0,
            "total_expenditures": 3869710,
            "latitude": 29.32215,
            "longitude": -98.54884,
            "city_project_no": null,
            "scope": null,
            "design_start": null,
            "design_end": null,
            "consultant": null,
            "contractor": null
        }
    ],
    "caveats": {
        "budget_field_is_a_recorded_zero": "The field named \"Total Budget\" is a recorded zero on most projects, not a blank. Nothing in the record says whether that zero means the project has no separate total budget or that nobody entered one, so this page says \"recorded as zero\" and never \"missing\". Every dollar figure published here uses the Bond Budget and Bond Expenditures pair, each printed beside its coverage rate.",
        "a_rate_lives_inside_one_pair": "Four divisions are refused, not one: Total Expenditures by Total Budget, Bond Expenditures by Total Budget, Total Expenditures by Bond Budget, and any of those summed citywide before dividing. A rate is computed only within a pair. The record does not document what separates the two pairs and this page does not guess.",
        "schedule_is_self_reported": "No project carries a real date; every recorded construction end is a season. Whether a project is on schedule is the City own assessment, published here as the City own assessment and not independently checked.",
        "no_project_is_past_its_stated_end": "Measured, and deliberately reported with its ambiguity. No project sits past its own stated end while still incomplete. That is consistent with the City keeping these dates current, and equally consistent with a date being rolled forward whenever a project slips. The record carries no history of previous end dates, so it cannot distinguish the two and neither can this page.",
        "three_district_columns": "The record carries three council district columns and they do not agree on every project. This page reads the one named Council District throughout, publishes the disagreement, and does not resolve it, because switching between them would move money between districts on no stated basis.",
        "district_money_not_split": "A project that spans several council districts, or is recorded as citywide, is never divided between them. The record does not say how the money divides and inventing a split would be our figure, not the City's.",
        "programmes_differ": "The two bond programs are at different stages of delivery. A single citywide spend rate blends them and describes neither, so both are always shown.",
        "not_a_ranking": "A district with more bond money recorded against it is not better served. Propositions fund particular kinds of asset and those are not evenly spread across the city.",
        "a_project_is_not_a_place": "The coordinate on a project is a single recorded point, not the extent of the work. A street or drainage project covers a corridor that no single pin describes. Where the City publishes a real alignment for a project the map draws that instead of a pin, and citywide programs are listed beside the map rather than plotted, because their recorded coordinates are a downtown cluster rather than a location of work.",
        "vendors_are_recorded_unevenly": "The City names a consultant or a contractor on some bond projects, in older files published alongside the current master list. That coverage runs backwards in time: it is nearly complete on the 2012 program, partial on 2017, and absent from the current list. A project with no vendor named here is one the record does not name a vendor for, not one that had none.",
        "approved_is_not_spent": "Approved money is what voters authorised for a project. Expenditure is what the City records having spent so far. Neither is a promise about what the finished work will cost."
    },
    "field_notes": {
        "duplicate_district_columns": {
            "columns": [
                "Council District",
                "CD",
                "CD2"
            ],
            "council_district_eq_cd": 329,
            "cd_eq_cd2": 347,
            "of": 370,
            "used": "Council District",
            "note": "The record carries three council district columns and they do not agree on every project. This tool reads the one named Council District throughout. There is no basis in the record for preferring another, and switching between them would move money between districts, so the disagreement is published rather than resolved."
        },
        "duplicate_budget_column": {
            "columns": [
                "Bond Budget",
                "Bond_Budget2"
            ],
            "agree": 370,
            "of": 370,
            "note": "Bond_Budget2 is identical to Bond Budget on every project. It is not used and adds nothing."
        },
        "contact_column_excluded": {
            "column": "CPO",
            "note": "The record names a capital projects officer and a direct phone number on every project. It is read by nothing here and appears in no cube, CSV or API response. Same rule as the permit record, which mixes company names with private individuals: this tool aggregates, and republishing 50 named City staff with their direct lines is not what it is for."
        },
        "no_data_dictionary": {
            "checked": "2026-08-30",
            "note": "Unlike the building permits package, this one publishes no data dictionary; its eleven resources are all format variants of the same layer. So nothing in the record documents what separates the Total and Bond money pairs, and this tool does not guess."
        }
    },
    "source": {
        "name": "City of San Antonio - Bond Project master list",
        "dataset": "https:\/\/data.sanantonio.gov\/dataset\/bond-project",
        "resource": "843caeb3-389d-416b-a78e-73e82975ec72",
        "api": "https:\/\/data.sanantonio.gov\/api\/3\/action\/datastore_search_sql",
        "cadence": "The City states this list is updated monthly."
    }
}